370 likes | 403 Views
Chapter 32. Floor Systems and Foundation Support. Links for Chapter 32. Slab Construction. Reinforcing Concrete. Crawl Spaces. Three Types of Foundations.
E N D
Chapter 32 Floor Systems and Foundation Support
Links for Chapter 32 Slab Construction Reinforcing Concrete Crawl Spaces
Three Types of Foundations • Types of foundations. There are three basic types of foundations. They are:Perimeter. A perimeter foundation creates a crawl space under the house. Most perimeter foundations are made of poured concrete or concrete block, although it is not unusual to find brick foundations in older buildings. Separate piers support girders and other concentrated loads within the perimeter.Slab. A slab built on grade functions as both the foundation and floor system. It is an economical type of foundation but can only be built in areas where soil conditions will permit construction. The slab must have deep footings under all the perimeter and bearing walls, and should always be at least 8 inches above grade.Basement. A basement foundation has higher walls than a perimeter foundation. It is built on a footing and has separate footings for support columns. The basement floor usually consists of a concrete slab poured after the footings and walls are completed.
Sources • http://www.diyinahour.com/foundations-explained.html
Slab Construction • Most foundation floors are concrete slabs • Usually 5” or 6” thick • Does not support walls • Poured as an extension of the foundation wall and footing
Slab Construction • Slab joints help control natural expansion and shrinkage of concrete slabs • Control joints are cut 6-8 hours after concrete is poured to be sure cracking occurs along the cut • Isolation joints separate a slab from another slab, wall, column or other structural part • Construction joints are made to support the joint between two slabs
Slab Construction • Slabs are placed above, below, or at grade level • Above grade slabs are indicated with a note • Below grade slabs are used in basements • At grade level slabs must be at least 8” above the grade to keep away from moisture
Slab Construction • Slabs are poured after the footings have been set • At least 4” of sand or gravel fill is placed under the slab • Slab fill is given as a note on the plans
Reinforcing Concrete • To help resist cracking, welded wire fabric is placed in the slab and noted as: • 6 X 12—W16 X W8 • 6 = longitudinal wire spacing • 12 = transverse wire spacing • 16 = longitudinal wire size • 8 = transverse wire size
Reinforcing Concrete • To help resist cracking, welded wire fabric is placed in the slab and noted as: • 6 X 12—W16 X W8 • W indicates smooth wire • D represents deformed wire
Reinforcing Concrete • To resist expansive soil, steel reinforcing bars are added to the slab • A 3” minimum coverage is needed if concrete is exposed to earth • A 2” minimum coverage is needed in basements • A 1 1/2” coverage is needed when concrete is not exposed to earth
Reinforcing Concrete • Post-tensioning is used when concrete is poured on unstable soil • Steel tendons are placed in the concrete as it is poured • About 3 to 10 days later the tendons are stretched creating an internal compressive force that helps the concrete resist cracking
Reinforcing Concrete • Flat slab and ribbed slab are most common forms of post-tensioned concrete • Flat slab tendons range from 3/8” to 1/2” and are spaced 5’-0” to 9’-0” apart • A ribbed slab uses ribs or beams under the slab to reduce the span of the slab over the soil and increase support
Reinforcing Concrete • Slabs are placed on 6 mil polyethylene sheet plastic to protect against ground moisture • Depending on the climate, additional rigid insulation is added under the slab • Plumbing and heating components are placed under the slab ( fixture kept in Plan)
Reinforcing Concrete • Dimensions are added to these components • Outline of slab • Interior footing locations • Changes in floor level • Floor drains • Exterior footing locations
Crawl Spaces • Crawl spaces are at least 18” from bottom of floor and 12” from bottom of joists • Floor joists span the foundation walls • Usually build from 2 X 6 to 2 X 12 or from engineered lumber • Nailed to pressure-treated sill plate or flush to the sill plate
Crawl Spaces • A plywood subfloor is placed on the joists • Girders are used if the joist span distance is too great and are supported by a pier
Crawl Spaces • Beams are used instead of joists in post-and-beam construction • The subfloor is made of 2 X 6 T & G boards or 1 1/8” plywood • Subfloor is glued to the beams • Beams are supported by posts if span is too great
Crawl Spaces • If the site is sloped the floor and foundation methods can be combined