150 likes | 490 Views
PELC Conference 2005. Start with a Vision in Mind BP Greater Plutonio Project. 7 th April 2005. Andy Till Angola DCT Program Manager BP Exploration. Background. Block 18 – 6 deepwater fields operated by BP FPSO – Floating production, storage & offloading vessel 300m Long , 250kbbls / day
E N D
PELC Conference 2005 Start with a Vision in MindBP Greater Plutonio Project 7th April 2005 Andy Till Angola DCT Program Manager BP Exploration
Background • Block 18 – 6 deepwater fields operated by BP • FPSO – Floating production, storage & offloading vessel • 300m Long , 250kbbls / day • EPCm contract with Kellogg Brown & Root, UK • FPSO Hull built by Hyundai Heavy Industries, Korea • First Oil Q2 2007 • BP investment of $3.3b
Learning Cycle • Planning • Standards • Specifications • Doing • Contracts • Data Collection Tools • Reflecting • Assurance • Audit • Linking • Cleansing • Correction • Vision • Planning
GPP Information management (Planning) • Define Statement of Requirements during early stages of project (pre-feed) • Agree standards i.e. ISO 15926 • Agree project data and document requirements • Write the requirements in to the contract • Handover requirements (Responsibilities / Accountabilities) • Detailed standards (numbering / handover) • Clear Data Model • Early Visibility of Data
V Document Vault Document Vault Oracle Data Vault Oracle Data Vault - Processes Engineering Data & Relationships Document Meta-Data Supplier SDRL Documents Supplier Electronic Documents SDRL Document Register EIHS Templates and SDRL Data Requirements Data Collection (Doing) Import or Data Entry Document Posting/ Review Suppliers ICT Phasset P-H Documentum Propid KBR
Close collaboration with: (Reflecting) • KBR – EPCm Contractor • Pearson-Harper – Validation and Content & Data Collection Tool • Aveva – 3D Model & Engineering Portal People Process Technology
What is your paradigm? Electronic Data & Documents Single window Global Access
People Process Technology Conclusion • Write requirements in to the contract (2 Years 3 months to polish the data) • Comprehensive information set available for HUC and Operations (required detail in EIHS) • Confidence the information set will be complete for 1st Oil (data has been validated) • Any electronic system is only as good as the data entered (consistency and cleansing) • Angola has only scratched the surface of possibilities • Have a Vision