An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CREZ Implementation Project – Proposal for Discussion Warren Lasher Manager, System Assessment Regional Planning Group

  2. Purpose • To discuss how ERCOT will analyze proposed changes to the CREZ plan, and how to prioritize the plan components. • : Default • : Priority Regional Planning Group

  3. Part I: Plan Analysis • Default Projects • System Benefits • System Reliability • Priority Projects • System Benefits • System Reliability • Analysis using steady-state and economic system dispatch models, and analysis of West-North stability limit with added connections. Input databases will reflect existing system conditions. Regional Planning Group

  4. Part I: Plan Analysis • Changes in Approved Plan: • To reflect changed system conditions and requirements • To incorporate any potential cost-savings • To reflect routing considerations • Analysis using steady-state and economic system dispatch models. Input database includes all CREZ-approved equipment and full build-out of CREZ wind generation. • Changes evaluated on: • Cost savings • Time savings • Impact on system effectiveness Regional Planning Group

  5. Part I: Plan Analysis • Subject to guidance in the Final Order, proposed plan changes will be distributed using the RPG mailing list (similar to RPG projects). • Stakeholders will be given 14 days for comments. • ERCOT will conduct an independent evaluation. Regional Planning Group

  6. Part II: Prioritization • Default Projects: Underway • Priority Projects: First projects to have CCNs submitted (by Final Order docket 33672). • Priority Support Projects: A small set of additional projects required to maximize the benefits of the priority projects for existing wind projects. • Other Projects… Regional Planning Group

  7. Part II: Prioritization • Other Projects: • Staging analysis may be specified in the Final Order (docket 35665) • PUCT Staff Proposal for Prioritization: • ERCOT evaluation of the logistics of which facilities should be constructed before others • Additional mitigation of existing congestion • Beneficial development of the State’s highest quality wind resources • Geographic diversity of wind generation resources • Magnitude of benefit relative to costs Regional Planning Group

  8. Part II: Prioritization • Analysis will be conducted using a combination of steady-state, transient stability, and economic system dispatch models, with input databases: • Reflecting current system conditions • Reflecting the full CREZ build-out Regional Planning Group

  9. Part III: Additional Analyses • Reactive Equipment Specification (Static or Dynamic) • Series Compensation Regional Planning Group

  10. Questions? Regional Planning Group