SPIS-Elena - Tramways in Skåne

Explore the collaborative efforts in Skåne to develop an energy-efficient light rail network, focusing on common goals, optimized processes, and joint strategies. Learn about key projects, funding, and consortium organization.

spaz
Download Presentation

SPIS-Elena - Tramways in Skåne

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPIS-Elena - Tramways in Skåne Light rail day, 8 november 2011 Marcus Horning, project manager, SPIS-Elena

  2. Background the SPIS collaboration • Common study (2007). Region Skåne, Malmö, Lund, Helsingborg and the National Railway Administration • Analyzing: • Expected passengers • Economy • City development • Physical conditions in the cities • Environmetal effects • Congestion • Regional development

  3. Background the SPIS collaboration • Cooperation is formalized in 2010 with political steering committee • Partners: The Region of Skåne and the cities of Malmö, Lund and Helsingborg, in Sweden. • The SPIS investment programme consists of the coordinated planning and implementation of a new tramway network in Lund, Malmö and Helsingborg.

  4. Why joint venture? • Rather small systems in each city • One common system in the future • Common maintenance and operation in the future • Joint procurement – larger volume, better price • The same technique for track and vehicles • The same design principles • The same design guidelines

  5. Main projects in the SPIS- collaboration • New tramway line in Lund • Number of lines: 1 line • Number of stops: 9 • New trams: 8 • New tramway lines in Malmö • Number of lines: 2 lines • Number of stops: 35 • New trams: 23 • New tramway line in Helsingborg • Number of lines: 1 line • Number of stops: 13 • New trams: 11

  6. Elena application fall 2010 • ELENA application sent to EIB December 2010. May 2011 – application granted • 3,3 million euro til May 2014 • 90 % Elena 10% divided by all parties • 25 times the leverage factor must be met before project period ends - this means an investment of 83 million euro • Main purpose – to achieve energy efficient public transport!

  7. Elena application fall 2010 – energy savings

  8. Aims and goals - with SPIS-Elena • Energy efficient light rail in Skane – sustainable development • Optimize the cooperation of the partners involved and the implementation – save time and money • Investigate common questions – create synergy, one plattform • Collectively communicate the project - open source

  9. Consortium organisation Tramways in Skane Political steering committee of SPIS Head of chief committe of SPIS WP 1 Project management of SPIS-Elena WP 2 Vehicles WP 3 Financing WP 4 Design WP 5 Main-tenance WP 6Communication

  10. Staff and SPIS-office • Recruting staff • Project manager (100%) • Controller (50%) • Tendering expert (100%) • Tram expert (100%) • Project strategist (50%) • Communicator (100%) • Project coordinator 1 (100%) • Project coordinator 2 (100%) • Project coordinator 3 (100%)

  11. WP 1 Project management of SPIS-ElenaProject plan - Content • Coordinate and lead the work • Define administative processes • Budget and timeframe • Reporting • Budget - 142 000 euro

  12. WP 2 Vehicles Project plan - Content • Investigate system for – energy, technique, electricity etc • Defining maintence approach • Support for tendering preparation • Tendering • Ordering • Budget - 310 000 euro

  13. WP 3 Financing Project plan - Content • Financial strategy • Different financing alternatives • Negotiation package • Successive calculation • Investigation – traffic, stages, financing sources, alternative costs etc • Budget - 180 000 euro

  14. WP 4 Design Project plan - Content • Largest package • Links all WPs • Develop common standards – optimize together not seperatly • Define the most energy effective design – support model split to energy efficient public transport • Budget - 950 000 euro

  15. WP 5 Maintenance Project plan - Content • Long term package • Joint maintenance system – energy and resource effective life cycle • Innovative quality system – secures a reliable and attracitve system support the modal split • 60 000 euro

  16. WP 6 Communication Project plan - Content • Joint communication strategy – better effect, exchange of knowledge, effective use of resources • Strategy which connects goals, challanges and opportunites • Communication plans – different target groups • (Budget – 200 000 euro not Elena funding)

  17. Time plan 2011 2012 2013 2014 Maj Juni WP 1 Project managment WP 2 Vehicles WP 3 Finance WP 4 Design WP 5 Maintenance WP 6 Communication Today EIB report

  18. Thank you