This application outlines the projects and costs for the Corvallis Transit System's service enhancement, garage expansion, bus rebuilds, and bus stop amenities upgrades. It also includes tasks for fleet electrification, including power infrastructure and purchasing an electric bus.

stallings
Download Presentation

Presented to Benton County STIF Advisory Committee, March 4, 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Corvallis Transit System: Application for Statewide Transportation Improvement Fund Formula Funds Presented to Benton County STIF Advisory Committee, March 4, 2019

  2. Application Overview$3,956,700 in total project funds$3,056,700 from the 100% list (5 projects) $900,000 from the 130% list (1 project)

  3. 100% ListProject 1: Corvallis Transit System Service EnhancementTask 1: Operations - Sunday service, more hours and frequency, new routesProject Cost: $1,973,700Outcome Measures:326,737 Revenue Miles; 23,780 Revenue Hours; 356,700 Rides

  4. 100% ListProject 1: Corvallis Transit System Service EnhancementTask 2: Add Program Staff (1 FTE)Project Cost: $202,000 (two years)

  5. 100% ListProject 2: CTS and Philomath Connection Garage ExpansionUpgrade current City of Corvallis maintenance facility to accommodate large transit busesProject Cost: $550,000AdditionalLocal Funds: $15,000 for planning

  6. 100% ListProject 3: Mid-Life Rebuild for CTS BusesMid-Life transmission and engine rebuilds for five CTS Buses to extend useful lifeProject Cost: $200,000

  7. 100% ListProject 4: CTS Bus Stop AmenitiesImproved bus stop amenities such as lighting, trash receptacles, bike racks, benches and sheltersProject Cost: $76,000

  8. 100% ListProject 5: CTS Bus Stop AmenitiesWireless Infrastructure and Live Streaming Video for Bus Camera System Project Cost: $55,000

  9. 130% ListProject 1: CTS Fleet ElectrificationTask 1: Power infrastructure and charging system Project Cost: $90,000

  10. 130% ListProject 1: CTS Fleet ElectrificationTask 2: Purchase Electric BusProject Cost: $810,000