Ben Hansen PIP-II Machine Advisory Committee Meeting 25-27 March 2019

This document provides an outline of the PIP-II Cryoplant, including the scope of work, capacity and building requirements, and progress to date. It also discusses the collaboration between Indian institutions and Fermilab and the cryogenic controls scheme.

exley
Download Presentation

Ben Hansen PIP-II Machine Advisory Committee Meeting 25-27 March 2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ben Hansen PIP-II Machine Advisory Committee Meeting 25-27 March 2019 PIP-II Cryoplant

  2. Outline • Scope of Work • Cryoplant Capacity Requirements • Cryoplant Building Requirements • Progress to Date • Summary Hansen | Cryoplant P2MAC meeting

  3. Scope and Deliverables – In-Kind • DAE India • Helium Cryogenic Plant Purchased from Industry • Coldbox • Warm Compressor System • Jointly developed Cryoplant specification between DAE/India and Fermilab Cryogenic Systems SPMs during long-term visit • Joint Technical Evaluation of proposals. Commercial evaluation in progress by DAE/India ESS Compressor Room ESS Coldbox Hansen | Cryoplant P2MAC meeting

  4. Indian Institutions and Fermilab Collaboration (IIFC) • Communication is Key, weekly meetings with DAE/India Cryogenics SPC counterpart, maintain detailed action item list and meeting minutes • Face-to-face visits throughout the contract • 1-2 long-term visitors (engineers) from DAE/India will be collaborating with Fermilab locally on the PIP-II Cryoplant Hansen | Cryoplant P2MAC meeting

  5. Scope and Deliverables - Fermilab Services: • Cryoplant equipment rigging • Cryoplant Installation New Equipment: • Liquid Helium (LHe) Dewar • Helium Purifier • Helium Transferline from CP to Dewar • LN2Transferline from Dewar to Purifier • Controls and Instrumentation for Fermilab scope Existing/Repurposed Equipment: • Recovery/Purification Compressor • 7x Gas Helium (GHe) Storage Tanks • Liquid Nitrogen (LN2) Dewar Hansen | Cryoplant

  6. Cryoplant - Block Diagram • Interfaces are tabulated and tracked in: ED0007569 – PIP-II Interface Control Document – Cryogenic Plant Vendor* FNAL CryoP FNAL CF FNAL CDS * Cryoplant Vendor work managed by IIFC with Fermilab Involvement Hansen | Cryoplant

  7. Cryogenic Controls Scheme Hansen | Cryoplant P2MAC meeting

  8. Cryomodule Heat Loads • All sources were tabulated and based on experimental results or analysis • The primary heat load sources include: • Cavity dynamic heat loads • Current Leads • RF Couplers • Conduction heat leak • Radiation from thermal shield • All heat load information is documented in ED0008200 Q0 650MHz Hansen | Cryoplant P2MAC meeting

  9. Cryomodule Heat Loads • The Cryoplant design is dominated by the 2K heat load • The 2K heat load is dominated by cavity performance • Cavity heat loads are based on the expected CM installed Q0 factors and operating gradient *See ED0008200 for detailed individual cavity parameters Hansen | Cryoplant P2MAC meeting

  10. Capacity Safety Factors • Safety factors, representing the heat load uncertainty are explicitly defined to avoid mis-sizing • Under-sizing leads to expensive upgrades or lower operating energy • Over-sizing can lead to operational issues of capacity control, inefficiencies and unnecessary higher costs 𝐹𝑆 = 1.3, static heat load safety factor 𝐹𝐷 = 1.15, dynamic heat load safety factor 𝐹𝑂 = 1.1, operational safety factor Heat Load Summary: Hansen | Cryoplant P2MAC meeting

  11. Cryoplant – Process Requirements • A combined thermodynamic and hydraulic analysis of the CDS and CM system was used to refine the Cryoplant requirements • 2K heat load is a combination of isothermal and non-isothermal • The CDS heat load to 4.5 K supply and the JT Heat Exchanger effectiveness, impacts the cavity supply temperature and therefore the LHe quality (2K flow rate) Cryoplant Requirements: Hansen | Cryoplant

  12. Cryoplant Building Requirements - Risk Mitigation • We have a high degree of confidence that the PIP-II Cryoplant Building requirements can support a cryoplant with a capacity up to 3 kW at 2K [1] • Confidence is based on the vendor proposed equipment and what we know about the ESS specified cryoplant and building ESS Cryoplant Requirements: J. Weisend et. al. Hansen | Cryoplant P2MAC meeting

  13. Cryoplant Building Requirements • Vendors submitted detailed equipment requirements with proposals • Worst case vendor requirements used to define the Cryoplant Building Requirements (ED0006719-TRS-Cryoplant Building) • An independent review of the TRS was carried out and action items addressed (ED0008588) • The ESS Cryoplant vendor specified ~identical equipment, providing a level of confidence in our building requirements … Hansen | Cryoplant P2MAC meeting

  14. Cryoplant Building – Coldbox Size and Layout Vendor 1 • Equipment Weight: • 56000 kg (Coldbox) • Crane Capacity: • 22,679 kg • Crane Hook Clearance: • 26 ft Hansen | Cryoplant P2MAC meeting

  15. Cryoplant Building – Compressor Size and Layout Vendor 1 • Equipment Weights: • 12,000 kg (SP Compressor) • 12,000 kg (LP Compressor) • 12,000 kg (HP Compressor) • 12,000 kg (HP oil and gas unit) • 18,000 kg (SP&LP Oil and Gas Unit) • 2,500 kg (Coalescer Skid) • 3,700 kg (Oil Adsorber) • 1,700 kg (GMP) • 900 kg (Dryer) • Crane Capacity: • 22,679 kg • Crane Hook Clearance: • 26 ft Hansen | Cryoplant P2MAC meeting

  16. Cryoplant Building – Coldbox Layout Vendor 2 • Equipment Weight: • 75000 kg (Coldbox) • Crane Capacity: • 22,679 kg • Crane Hook Clearance: • 26 ft LastName | Your System Name P2MAC meeting

  17. Cryoplant Building – Compressor Size and Layout Vendor 2 Equipment Weights: • 35,000 kg (SP Compressor) • 35,000 kg (LP Compressor) • 35,000 kg (HP Compressor) • 15,000 kg (HP oil and gas unit) • 15,000 kg (LP Oil and Gas Unit) • 15,000 kg (SP Oil and Gas Unit) • 13500 kg (ORS, Dryer and GMP) Crane Capacity: • 22,679 kg Crane Hook Clearance: • 26 ft Hansen | Cryoplant P2MAC meeting

  18. Requirements - Layout • Building layouts were generated based on the two vendor proposals. • The largest of the two vendor equipment sizes drove the overall Cryoplant Building size • Provisions made for a spare compressor and a 4.5 K Coldbox Coldbox Station 4.5K Coldbox (space) Compressor Station Mech Room LHe Dewar CDS Distribution Box Control Room Purification System Hansen | Cryoplant P2MAC meeting

  19. Requirements - Layout 111’ 151’ Coldbox Oil Unit (spare) LP/SP Oil Unit HP Oil Unit 55’ Vendor 1 157’ 111’ Coldbox 55’ • Primary difference is Vendor 2 did not combine the SP and LP oil and gas skid Vendor 2 Hansen | Cryoplant

  20. Requirements – Layout • Actively working with building contractor to incorporate their model and verify space requirements • Modeled in primary pipe headers to verify space requirements, keep away zones and column support requirements Hansen | Cryoplant P2MAC meeting

  21. Summary • Cryoplant requirements defined and joint specification written • Proposals were received, technical evaluation complete and bid evaluations in progress by DAE/India • Cryoplant Building Requirements are defined, independently reviewed and action items addressed • Preliminary building layout defined • On track for CD-2/3a and look forward to your feedback Hansen | Cryoplant P2MAC meeting

  22. End Hansen | Cryoplant P2MAC meeting