1 / 17

Earned Value Analysis by John Cornman

Earned Value Analysis by John Cornman. Introduction. “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way.

sunee
Download Presentation

Earned Value Analysis by John Cornman

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Earned Value AnalysisbyJohn Cornman

  2. Introduction • “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its completion date and final cost, and provide schedule and budget variances along the way. • Based on just 3 data points, it can provide consistent, numerical indicators with which you can evaluate and compare projects.

  3. The 3 fundamental metrics • Budgeted Cost of Work Performed. • Budgeted Cost of Work Scheduled. • Actual Cost of Work Performed.

  4. Budgeted Cost of Work Performed • This is the “Earned Value.” • Abbreviated as BCWP. • For completed work, it is the cost originally budgeted to accomplish that work. • “How much work was actually done?”

  5. Budgeted Cost of Work Scheduled • Abbreviated BCWS. • It is the total budgeted cost up to the analysis date. • Approximated by the total budget multiplied by the fraction of total project duration at the analysis date. • “How much work should have been done?”

  6. Actual Cost of Work Performed • Abbreviated ACWP. • What it actually cost to accomplish all the work completed as of the analysis date. • “What did the work that was actually done actually cost?”

  7. Derived Metrics • Schedule Variance (SV) • Schedule Performance Index (SPI) • Cost Variance (CV) • Cost Performance Index (CPI)

  8. A Few More Acronyms • BAC - Budget At Completion • = Total Original Budgeted Cost • Same as BCWS at completion • EAC - Estimate At Completion • = Cumulative Actuals + Estimate-To-Complete • VAC - Variance At Completion • = Forecast of final cost variance

  9. Doing The Math • SV = BCWP - BCWS • Negative means Behind Schedule • SPI = BCWP / BCWS • Less than 1.00 means Behind Schedule • CV = BCWP - ACWP • Negative means Over Budget • CPI = BCWP / ACWP • Less than 1.00 means Over Budget • EAC = BAC / CPI

  10. An Example: Lemonade • Make 1,000 cups over 50 days • Steady rate of 20 cups per day • Budgeted cost per cup is $0.50 • Total project budget is $500

  11. Lemonade Progress • At end of day 10: • 150 cups have been made • Total actual cost is $90 (ACWP)

  12. Lemonade Status • BCWS = $100 • 10 days x 20 cups per day x .50/cup budget • BCWP = $75 (Earned Value) • 150 cups x .50/cup budget • SV = BCWP - BCWS = -$25 • SPI = BCWP / BCWS = 0.75 • CV = BCWP - ACWP = $75 - $90 = -$15 • CPI = BCWP / ACWP = 0.833

  13. Lemonade Forecast • EAC = BAC / CPI = $500 / 0.833 = $600 • VAC = BAC - EAC = $500 - $600 = $100 (unfavorable) • Schedule at Completion =50 / SPI = 50 / 0.75 = 66.67 days

  14. MS Project 98 Support

  15. Five Simple Criteria forEarned Value Applications 1. Define (scope) the project. . .with a WBS 2. Plan and schedule the project scope 3. Budget cost account plans to functions 4. Establish and maintain a performance baseline 5. Monitor performance and forecast final results Fleming & Hoppleman. 1996. Earned Value Management. PMI

  16. Earned Value Management http://www.acq.osd.mil/pm/

More Related