1 / 10

APS Dual Site ECC

CIPC Confidentiality: Public Release. APS Dual Site ECC. Primary Site Shutdown/Restart. The Need for a Power Outage. Information Services installing a new UPS for Business Continuity. Two feeder breakers identified as needing replacement.

svea
Download Presentation

APS Dual Site ECC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIPC Confidentiality: Public Release APS Dual Site ECC Primary Site Shutdown/Restart

  2. The Need for a Power Outage • Information Services installing a new UPS for Business Continuity. • Two feeder breakers identified as needing replacement. • Power outage to entire building during breaker work. • ECC Migration to alternate site

  3. EMS/ECC Shutdown • Failover primary EMS application functions to alternate site. • Failover front-end processors to alternate site. • Failover EMS business applications to alternate site. • Failover primary EMS network communications to alternate site. • Ensure ECC personnel onsite at DV-ECC and ready for site cutover. • Prepare and test Avtec communications for transition to alternate site.

  4. EMS/ECC Shutdown • Ensure EMS support personnel are at both sites and ready for cutover. • Transfer Avtec communications from primary site to secondary site. • Shutdown ECC consoles at the primary site. • Ensure cutover is complete. • Obtain ECC approval and power down all remaining EMS servers and related equipment.

  5. EMS Functional/Logical Distribution

  6. EMS/ECC Restart • Ensure EMS support personnel are at both sites and ready for cutover. • Restart and validate operation of computer network switches at primary site. • Restart and validate operation of the Avtec communication equipment at primary site. • Restart and validate operation of EMS Business application services at primary site. • Failover primary EMS network communication to primary site.

  7. EMS/ECC Restart • Power up and validate EMS application running in backup configuration from primary site. • Transfer Avtec communications from secondary site to primary site. • Failover front-end processors to primary site and validate proper scanning. • EMS servers functionally evaluated in backup configuration at primary site. • ECC move from secondary location to primary location.

  8. Learning's and Action Items

  9. Learning's and Action Items

  10. Conclusion • Breaker replacement was successful. • Processes and scripts have demonstrated success • APS EMS/ECC functionally split between sites.

More Related