CIPC Confidentiality: Public Release. APS Dual Site ECC. Primary Site Shutdown/Restart. The Need for a Power Outage. Information Services installing a new UPS for Business Continuity. Two feeder breakers identified as needing replacement.
E N D
CIPC Confidentiality: Public Release APS Dual Site ECC Primary Site Shutdown/Restart
The Need for a Power Outage • Information Services installing a new UPS for Business Continuity. • Two feeder breakers identified as needing replacement. • Power outage to entire building during breaker work. • ECC Migration to alternate site
EMS/ECC Shutdown • Failover primary EMS application functions to alternate site. • Failover front-end processors to alternate site. • Failover EMS business applications to alternate site. • Failover primary EMS network communications to alternate site. • Ensure ECC personnel onsite at DV-ECC and ready for site cutover. • Prepare and test Avtec communications for transition to alternate site.
EMS/ECC Shutdown • Ensure EMS support personnel are at both sites and ready for cutover. • Transfer Avtec communications from primary site to secondary site. • Shutdown ECC consoles at the primary site. • Ensure cutover is complete. • Obtain ECC approval and power down all remaining EMS servers and related equipment.
EMS/ECC Restart • Ensure EMS support personnel are at both sites and ready for cutover. • Restart and validate operation of computer network switches at primary site. • Restart and validate operation of the Avtec communication equipment at primary site. • Restart and validate operation of EMS Business application services at primary site. • Failover primary EMS network communication to primary site.
EMS/ECC Restart • Power up and validate EMS application running in backup configuration from primary site. • Transfer Avtec communications from secondary site to primary site. • Failover front-end processors to primary site and validate proper scanning. • EMS servers functionally evaluated in backup configuration at primary site. • ECC move from secondary location to primary location.
Conclusion • Breaker replacement was successful. • Processes and scripts have demonstrated success • APS EMS/ECC functionally split between sites.