Project Management LectureNetwork Analysis
Introduction Project planning Gantt chart and WBS Project planning Network analysis I Project planning Resource analysis Risk management Quality Budgets and cost control Project teams Plan • Introduction • Project planning • Gantt chart and WBS • Project planning • Network analysis I • Project planning • Network analysis II
Iterative Process • The plan will evolve as the project evolves • The plan is reviewed and updated as more information becomes available and uncertainties become less uncertain
Use Case • Describes a unit of functionality from a users perspective • May be text or diagram • Therefore they provide a good tool for Project Task Planning • They also can determine the nature of the project process • How many development iterations?
Use Case Example – Big John’s • Each Use Case Shown can be shown as activities in the PBS • The prioritisation can be used to describe the activities for two development iterations • This will be significantly different to the process if only one iteration was used
Gantt chart disadvantages • Not ideal for showing inter-relationships • Locating an activity requires three simultaneous decisions: • Method • Time • Resources
Complexity • Number of tasks? • Number of people? • Size of Budget? • Number/Nature of constraints • Dependencies between tasks
Why Network Diagrams? • Splits up the decision making process into • Method/logic - the order in which tasks have to be completed • Time – estimates for the time to completion can be added to each task • Resources – these can be added and then analysis carried out
Two Methods • Activity on Arrow • Traditionally the preferred method • Activity on Node • More popular these days • Supported by most Project Management software tools (i.e. MS Project)
Activity on Arrow • Arrows are used to represent an activity • Circles are used to represent the points where activities meet • i.e. the dependency between activities
Activity on Node • Activities are represented by boxes • Dependencies are represented by arrows joining the boxes
Dependency Example • Task B cannot start until Task A is complete • Activity on Node • Activity on Arrow • Task B cannot start until Task A is complete • Activity on Node
More complex example • Four activities/tasks: • A, B, K, L • Activity K is dependent on activity A • Activity L is dependent on activities A and B
The problem with AoA • The same example in AoA • The same example in AoA Wrong… • Activity K is dependent on activity A • Activity L is dependent on activities A and B Right
Exercise 1 • Draw the following: • Activity K is dependant on Activity A • Activity L is dependent on Activity B • Activity M is dependent on Activity A and B
Exercise 2 • Draw the following: • Activity K is dependent on activities A and B • Activity L is dependent on activities B and C • Activity is dependent on activity B
Drawing the network • Direction • The flow of work is from left to right • Identifying Tasks • Each task is given a unique ID number • ID number is often given in WBS
Scale • Diagram is not drawn to scale • Length and size do not matter • They have no meaning
Errors in Logic • Looping • Due to a mistake in drawing or to errors in identifying dependent activities
Errors in Logic • Dangling • Usually occur when activities are added as an afterthought • Can be avoided by using a single finish node
Project planning Network analysis I Project planning Network analysis II Project planning Resource analysis Risk management Quality Budgets and cost control Project teams Plan • Introduction • Project planning • Gantt chart and WBS • Project planning • Network analysis I • Project planning • Network analysis II Final thought for the day:Erm…