1 / 52

Introduction To An Example Project

Chapter 4. Introduction To An Example Project. Prepared by: Alaa El Shorafa Munther Abdel-Hadi Ahmed El Zinati Shukri El Zaza Supervision : Dr. Kamaleen Sha’th. Introduction.

sveta
Download Presentation

Introduction To An Example Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 4 Introduction To An Example Project Prepared by: Alaa El Shorafa Munther Abdel-Hadi Ahmed El Zinati Shukri El Zaza Supervision : Dr. Kamaleen Sha’th

  2. Introduction This chapter introduces an example practical implications of concepts and procedures described in the chapters that follow. Chapter 4

  3. Introduction Chapter Objective: • Technical description of the project and its life cycle. • Actual professional construction managment proposal followed by a copy of the procedure outline. Chapter 4

  4. Introduction 3. Ways in which the owner may construct the project, including the use of a single general contractor , a design construct firm or a developer. 4. Alternate ways to provide for overall managment, contract administration and quality control. Chapter 4

  5. Objective 1 1-1 ProjectTechnical Description The Easy way Food Company wants to build a new warehouse with 150,000 ft2 =13500m2 that will provide storage for grocery and non-food items. Chapter 4

  6. Objective 1 The work included mainly: • The concrete work • The Steel works • The required utilities Chapter 4

  7. Objective 1 Chapter 4

  8. Objective 1 1-2 Project Life Cycle • Concept and feasibility study • Engineering & Design • Procurement • Construction • Start-up & Implementation Chapter 4

  9. Objective 1 A. Concept & Feasibility Study In this phase the Design & Construction Dept. Based upon the requirement of the Operating Division did the following: • Initial Feasibility study; • Conceptual drawings Chapter 4

  10. Objective 1 • Alternate design-construct schedule • Sequantial schedule (traditional approach), if time available 12 months or more. • Phased schedule, if time only 10 months available for desgin & construction. Chapter 4

  11. Objective 1 • Sequantial schedule This mothed include : • Plans and specifications prepared by local Arch. • Constuction performed under a single lump-sum contract • Barring changes after award • The cost of project be fully known before constrcution begins Chapter 4

  12. Objective 1 Chapter 4

  13. Objective 1 Owner’ Options for the phased Schedule • Turnkey • Traditional with a negotiated construction contract • Professional construction management Chapter 4

  14. Objective 1 • Owner’s Selection The owner selected the professional construction approach based on the following: • Capabilities of the firm in the area • Easy way's own internal qualifications and objectives Chapter 4

  15. Objective 1 B. Engineering & Design In this phase the CMC ( Construction Management & control, Inc.) • Prepared procedure outline spelling out the relationship between the owner, architect and construction management • Developed procurement schedule • Finalized the bid packages Chapter 4

  16. Objective 1 • Developed CPM control schedule. • Prepared fair-cost estimate. • Set up the project control system. Chapter 4

  17. Objective 1 Several value-engineering alternates were reviewed. • Some of these alternate are chosen and included in the final plan a specification. • Other included as alternate in the bidding documents to enable the contractors to determine the least costly solution. Chapter 4

  18. Objective 1 C. Procurement • In this approach CMC acting as an a gent to the owner. • Procurement overlapped both design and construction. Chapter 4

  19. Objective 1 For this project 10 contractors were chosen: • Site earthwork • Foundation & slab concrete • Structural steel • Pre-cast concrete walls • Fire protection • Plumbing, heating, Ventilating and air conditioning • Electrical • Roofing • Special floors • Building Finish Chapter 4

  20. Objective 1 D. Construction This phase including • Awarding the contract • Appointed the required clerk typist • Initial layout handled by surveyor • Testing as the soil • The A/E visit the work site frequently • Contractor were directed through the job-site office Chapter 4

  21. Objective 1 F. Start up& Implementation CMC responsible was lie on • Makes the owner familiarize with operating equipment. • Trouble shooting through the start up phase. Chapter 4

  22. Objective 2 2-1 The Successful Proposal • The owner requested proposal from two general contractors • Technical & financial evaluation took place by the owner to choose one of them Chapter 4

  23. Objective 2 The successful proposal consists the following items: • A letter outlines the Proposed services and quotes a fixed fee for the home office services • Preliminary schedule • Estimate of construction management costs • Project organization chart • Preliminary CPM diagram Chapter 4

  24. Objective 2 A. Proposed Serives: The proposal shows the CMC will provide the following services: • Prepare control schedule (showing bid package duration) • Develop bids packages • Prepare bidder list • Prepare cost estimate Chapter 4

  25. Objective 2 5.Receive, review and evaluate bids 6.Manage, coordinate and inspect the work • Coordination of the contracts • Monitoring the schedule of individual phases • Making recommendation for adjusting the work • Preparing progress reports Chapter 4

  26. Objective 2 • Reviewing the progress payment • Obtaining the required shop drawing and forwarding them to the A/E for approval • Inspecting the quality of material and workmanship 7. Provide home-office support (Will be utilized on as required basis) Chapter 4

  27. Objective 2 Fig.(4-4) B. Preliminary Schedule Chapter 4

  28. Objective 2 B. Preliminary Construction Cost Estimate Fig.(4-5) Chapter 4

  29. Objective 2 C. Estimate of Construction Management Costs • Filed Cost • Fixed fee • ffice overhead • profit Chapter 4

  30. Objective 2 Fig.(4-6) Chapter 4

  31. Objective 2 Fig.(4-7) D. Project organization chart Chapter 4

  32. Objective 2 Fig.(4-8) E. Preliminary CPM Schedule Chapter 4

  33. Objective 2 2-2 The Procedure Outline It illustrates the duties and responsibilities during planning, procurement and construction phases as follows: Chapter 4

  34. Objective 2 2.2.1. General • Purpose: establishing procedures for performance by professional construction management • Names & Addresses of the Key Personnel • Owner • Construction Manager • Architect C. Correspondence Chapter 4

  35. Objective 2 D- Report to owner which includes: • Monthly progress report: this report covering significant phases of monthly activity. • Weekly field activity report: this report discuss weekly field activity. • Weekly force report: this report listing number of CM and contractor personal on the job. • Contract status report (monthly contact status report). Chapter 4

  36. Objective 2 2.2.2. Relationships with architects and owner The following items are listed to clarify the relationships and responsibilities • Special conditions and general conditions. • Drawing and specifications • Substitution policy • Shop drawings Modification and changes Chapter 4

  37. Objective 2 • Building permit( the architect will contact the proper authorities to obtain the building permit. Surveying and testing laboratories • Proposed bid package • Approval bid list • Approval bid document • On site inspection • Plan interpretation Chapter 4

  38. Objective 2 2.2.3. Home office responsibilities CM will be responsible for the followings: • Overall job schedule • Fair cost estimates • General home- office- supervision which include: • Developing a detailed scope and bidding document • Evaluate bids preparing recommendation to award the contract • Monthly progress report Chapter 4

  39. Objective 2 2.2.4. Field responsibilities The field construction manager responsibilities include but not limited to the following: • Assist in evaluation of bids • Manage, coordinate, and inspect al work performed by contracts. • Administer and direct the testing lab and surveying contacts jointly with the architect Chapter 4

  40. Objective 2 2.2.5.Reports and correspondence summary Chapter 4

  41. Objective 3 Alternate way for Construction the Project Easy way can choose between : A cost-plus a fee Fixed Price Guaranteed maximum contract Design-Construct Developer Chapter 4

  42. Objective 3 3.A- Fixed Price Contract • Separate contract would be negotiated with the A/E for completion the conceptual and detail design. • Contractor will be selected in accordance with the procedure adopted by Esay way Co. • The successful general contractor will usually plan to perform most of the work Chapter 4

  43. Objective 3 3.B- Guaranteed Maximum Price • Used when shortest schedule are economically imprtantant • The owner supplies the contractor with the conceptual plans and specifications Chapter 4

  44. Objective 3 • A negotiated GMP is developed which often includes a fixed fee for home-office services and profit. • Used when shortest schedule are economically imprtantant. • The owner supplies the contractor with the conceptual plans and specifications. Chapter 4

  45. Objective 3 3.C- Cost-Plus-Fixed Fee • Used when the project scope is not fully developed and the overall minimum schedule is important. • The contractor will reimburse the field cost and negotiated a fixed fee for home office cost and profit. Chapter 4

  46. Objective 3 • The owner has maximum opportunity to participate in the management of the project • The owner assumed all of the price risk Chapter 4

  47. Objective 3 3.D-Design-Construct • Used when the initial project scope must be sufficiently clear so that both parties understand their responsibilities and risks • A single firm provide both design and construction work • Phased program used in order to achieve earliest completion Chapter 4

  48. Objective 3 3.E- Developer • Combine skills of construction manager, design contractor and real state investor • The developer will normally own or control a parcel of land • Easy way could also contract with a developer to build a warehouse based upon their design criteria Chapter 4

  49. Objective 3 • It would be then lease the facility for an extended period of time or to purchase • In recent years developers has proven to be extremely marketing, cost conscious. • Operationally many developer will hire contractors to manage the construction manager. • The developer will be very active in performing value engineering studies, managing the design work. Chapter 4

  50. Objective 4 Management, field administration, and quality control • Many repeat owners have their own staff to provide these services. • Others will delegate the responsibility to the architect, engineer, or to construction manager. Chapter 4

More Related