批量为 5 ,平行 - 顺序移动方式图解. 工序. 01 02 03 04. 0. 157. 第二题解: 1 、先按 EDD 规则求加工顺序. 2 、再按 SPT 规则调整加工顺序. 第三题解:先检查最优解的条件是否满足:. 可见满足最优解条件: min t cj ≥max t bj. 把三台设备转化成两台假象设备: t Gj = t aj + t bj ; t Hj = t cj + t bj. 用约 - 贝扩展规则求得最优加工顺序: J8-J2-J9 -J7–J1-J5 –J3-J6-J4. 用哈姆表算法求各任务的流程时间:.

Download Presentation

157

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 批量为5,平行-顺序移动方式图解 工序 01 02 03 04 0 157

  2. 第二题解:1、先按EDD规则求加工顺序

  3. 2、再按SPT规则调整加工顺序

  4. 第三题解:先检查最优解的条件是否满足: 可见满足最优解条件:min tcj≥max tbj

  5. 把三台设备转化成两台假象设备:tGj= taj+ tbj; tHj= tcj+ tbj. 用约-贝扩展规则求得最优加工顺序:J8-J2-J9 -J7–J1-J5 –J3-J6-J4

  6. 用哈姆表算法求各任务的流程时间:

  7. 第四题解:① 关键任务法求加工顺序,确定关键任务:

  8. 关键任务:J6 • 满足:t1<tm条件的有:J2,J3,J5,J7,J9; • 满足:t1>tm条件的有:J1,J4; • 满足:t1=tm条件的有:J8 • 排序结果: J9-J2-J5-J7-J3-J6- J8-J4-J1; • 或: J9-J2-J5-J7-J3-J8-J6- J4-J1

  9. 第四题解:① 用最小排序系数法求加工顺序,计算排序系数:

  10. 按排序系数大小,求得最优加工顺序: • J8-J9-J7-J2-J1-J6-J5-J3-J4; • 用哈目标算法求各方案的流程时间:

  11. 作业五:1、代表产品法: • 求以代表产品表示的生产能力: • Fe=280×2×8×60×0.9=241920(分钟) • 求代表产品表示的计划产量: • N代=3×30/30+4×25/30+3+2×40/30=12万 • 求代表产品生产节拍: • r代=241920/120000=2.016 (分钟) • 求其它产品的生产节拍: • rA= 2.016×30/30=2.016 (分钟); • rB= 2.016×25/30=1.68 (分钟) • rD= 2.016×40/30=2.69 (分钟)

  12. 劳动量比重法: • 总劳动量=3×30+4×25+3×30+2×40 =360(万分钟) ka=90/360=0.25;kb=100/360=0.278 kc=90/360=0.25;kd=80/360=0.222 各产品分配的有效工作时间: Fea= Feka =241920×0.25=60480; Feb= Fekb =241920×0.278=67253; Fec= Fekc =241920×0.25=60480; Fed= Fekd =241920×0.222=53706

  13. 求各产品生产节拍: • rA= =60480/30000=2.016 (分钟); • rB= 67253/40000=1.68 (分钟); • rC= 60480/30000=2.016 (分钟); • rD= 60480/20000=2.69 (分钟)

  14. 作业 7 解:求生产比倒数: • XA:XB:XC=2000:3000:4000=2:3:4 • 求一个循环流程产量:2+3+4=9 • 各产品生产比倒数:1/2:1/3:1/4 • 列表确定一个循环流程内的投产顺序:

  15. 第9题解: • ①求各车间生产间隔期: • R装=4天; 由n加=3n装, • q=n/R=20/4=5件 (q=装配平均日产量), • R加=3R装=12天; 同理:R毛=4R加=48天 • ② 求各车间的提前期: • D装出=0; • D装投=T装=2天; • D加出= D装投+(R加-R装)+T保=2+(12-4)+0=10天; • D加投= D加出+T加=10+5=15天 • D毛出= D加投+(R毛-R加)+T保=15+(48-12)+0=51天 • D毛投= D毛出+T毛=51+12=63天

  16. ③ 求计划期各车间投入和出产累计号数: • N装投 = N装出+ q×D装投=300+5×2 = 310; • N加出 = N装出+ q×D加出=300+5×10=350; • N加投 = N装出+ q×D加投=300+5×15=375 • N毛出 = N装出+ q×D毛出=300+5×51=555 • N毛投 = N装出+ q×D毛投=300+5×63=615

  17. 10、解:用最小批量法求最小批量: Qmin=t调÷(ti×k)=40÷ (2× 0.08)=250 11、解 :先求出经济批量: 月计划产量为200,为保证批量与计划产量成整数倍,把批量调整为100。即月投产两批。

  18. 工序1-2 • ZT1=60(2 / 11-1/3)= - 9; • ZT2=40(2/11-0/3)=7; • ZT3=20(1/11-0/3)=2 • 工序2-3: • ZT1=60(1 /3-1/9)=13.3 • ZT2=60(0-2/9)=-13.3

  19. 60 120