Infrastructure Updates and Plans at DESY Hamburg

Explore the latest infrastructure developments at DESY Hamburg, including cleanroom reconstructions, new oven installations, and turbine testing. Get insights on surface preparation, tuning labs, and more.

svines
Download Presentation

Infrastructure Updates and Plans at DESY Hamburg

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Infrastructure @DESY status and plansAxel Matheisen DESY Overview on infrastructure @ DESY Infrastructure and up date/ grade Activities schedule

  2. Overview on infrastructure @ DESY General Infrastructure of DESY covers all subjects for development, fabrication and preparation of super conduction cavities, optimized for 1.3 GHz cavities with up to 9 cell (Well know) • EB welding machine and machine shop • Heat treatment from 1400C to 120 C baking • Surface preparation by buffered chemical polishing (BCP) and electro-polishing (EP) bench • Clean room with high pressure rinsing, chemistry stand and cleaning equipment • Tuning lab • Small chemistry lab TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  3. Overview on Infrastructure cont. TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  4. Overview on Infrastructure cont. TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  5. Infrastructure and up date/ gradeRe construction of cleanroom Outside view of the cleanroom Before TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  6. Infrastructure and up date/ gradeRe construction of cleanroom In between TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  7. Infrastructure and up date/ gradeRe construction of cleanroom • After re construction TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  8. Infrastructure and up date/ gradeRe construction of cleanroom Clean room inside before TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  9. Infrastructure and up date/ gradeRe construction of cleanroom Cleanroom inside during TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  10. Infrastructure and up date/ gradeRe construction of cleanroom • And after re construction TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  11. Infrastructure and up date/ gradeInstallation of a new 120 C baking oven outside view After Before TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  12. Infrastructure and up date/ gradeInstallation of a new 120 C baking oven 120 C baking oven inside view (location ISO 4) TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  13. Infrastructure and up date/ gradeTest of HPR 2 turbine with 20 nozzles Standard 8 nozzles 0. 4 mm ID~ 0,7 m3/hour Test 20 nozzles 0,4 mm ID ~ 2 m3/hour TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  14. Infrastructure and up date/ gradeTest of HPR 2 turbine with 20 nozzles Pressure vs. time 8 Nozzles Standard treatment Pressure vs. time 20 Nozzles test run of 5.5 hours TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2

  15. Activities schedule TTTC Meeting 2011 Milano 11.2.28 to 11.3.3 Axel Matheisen DESY Hamburg WG-2