AGNICO-EAGLE MINES

AGNICO-EAGLE MINES. CHESTERFIELD INLET MEADOWBANK SHIPPING PROGRAM 2007. MEADOWBANK PROJECT. ACCESS ROAD. N U N A V U T. BAKER LAKE. AIRPORT. BARGE/SHIPPING ACCESS. Chesterfield Inlet. CHESTERFIELD. SEASONAL SHIPPING SCHEDULED AIR ROUTE. MELIADINE WEST. MELIADINE EAST.

swann
Download Presentation

AGNICO-EAGLE MINES

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AGNICO-EAGLE MINES CHESTERFIELD INLET MEADOWBANK SHIPPING PROGRAM 2007

  2. MEADOWBANK PROJECT ACCESS ROAD N U N A V U T BAKER LAKE AIRPORT BARGE/SHIPPING ACCESS Chesterfield Inlet CHESTERFIELD SEASONAL SHIPPING SCHEDULED AIR ROUTE MELIADINE WEST MELIADINE EAST RANKIN INLET To Yellowknife AIRPORT To Winnipeg Hudson Bay 0 50 Kilometres 50 Miles 0 MEADOWBANK LOCATION

  3. MEADOWBANK SITE PLAN

  4. N 0.5 0 km Meadowbank Project – Description Mine Plan/Feasibility: General Arrangement Portage

  5. Meadowbank Project - Description Exploration Potential: Goose South Discovery

  6. BAKER LAKE FACILITIES

  7. EQUIPMENT REQUIRED FOR 2007 • 4 X 100 tons trucks • 1 Grader • 1 Loader • 1 Dozer • 8 Pick-up trucks • 1 Ambulance • 2 Cranes • Concrete mixers • Container handler • Pumps • Construction equipment • Concrete plant

  8. MATERIAL REQUIRED FOR 2007 • 4 600 tonnes of cement • Reinforced steel • 20 million litres of fuel • Steel plate for fuel tank construction • Wood for construction • Mill building material • Weather haven garage • 72 dormitory modules • Steel and plastic pipes • etc.

  9. 2007 CONTRACTS • Road • Site preparation • Tank Farm • Concrete work • Camp installation • Mill Building Installation

  10. ALL WHEATHER ROAD

  11. BRIDGE

  12. BRIDGE LAUNCHING

  13. BAKER LAKE TANK FARM

  14. MEADOWBANK MINE SITE

  15. MEADOWBANK CAMP EXPANSION

  16. MEADOWBANK SITE 2006

  17. DORMITORIES BEING MANUFACTURED

  18. DORMITORIES READY FOR TRANSPORT

  19. MATNA THANKS QUESTIONS ?