1 / 46

HQ01 Quadrupole: Test Results & LHC Upgrade

Explore HQ01 quadrupole magnet test results for LHC's upgrade, supported by US Department of Energy and LARP program.

swhite
Download Presentation

HQ01 Quadrupole: Test Results & LHC Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The HQ Program and Test results of HQ01 - a 120 mm 15 T Nb3Sn Quadrupole for the LHC Upgrade Shlomo Caspi August 24, 2010 CERN LBNL: B. Bingham, D. Cheng, D.R. Dietderich, H. Felice, P. Ferracin, R. Hafalia, C.R. Hannaford, J. Joseph, J. Lizarazo, G. Sabbi and X. WangS BNL: M. Anerella, A. Ghosh, J. Schmalzle and P. Wanderer FNAL: G. Ambrosio, E. Barzi, R. Bossert, G. Chlachidze, V.V. Kashikhin and A.V. Zlobin • This work is supported by the Office of Science, High Energy Physics, U.S. Department of Energy through the US LHC Accelerator Research Program (LARP)

  2. Outline S. Caspi • Introduction – The LARP program • The HQ magnet • Test results – HQ01a, HQ01b • Conclusions and Future Plans

  3. LARP – Program Goals LHC Accelerator Research Program (LARP): • Started in 2004, expected to be completed around 2014 • Collaboration of four national Labs: BNL, FNAL, LBNL, SLAC • Funding level: $12-13M/year (FY06-FY10) Program Goals: • Extend and improve the performance of the LHC • Maintain and develop US Labs capabilities • Advance international collaboration on large accelerator projects Magnet Goals: • Demonstrate that Nb3Sn technology is a viable option for the LHC phase II upgrade. S. Caspi

  4. LARP - Magnet R&D Program • 1. Nb3Sn Technology - TQ • Conductor studies • Coil fabrication • Mechanical support • Modeling tools • Quench protection Reached 238 T/m • 2. Length scale-up - LQ • Coil technology • Quench protection • 3. Design optimization - HQ • Larger aperture • higher energy and forces • Accelerator quality S. Caspi

  5. HQ Program & Targets Program • Part of the US LHC Accelerator Research Program (LARP) • Develop Nb3Sn quadrupole magnet for the LHC luminosity upgrade. Magnet • Extend Nb3Sn magnet technology: • from 1 m long, 90 mm bore, 13T -> TQ – field quality • to 1 m long, 120 mm bore, 15T -> HQ + field quality • HQ operating point 80% of ss: • 160 (T/m) at 4.4K • 175 (T/m) at 1.9K • Good memory – no retraining Conductor • Evaluate different strands (54/61 and 108/127 filaments). S. Caspi

  6. The HQ Collaboration Program • A collaboration between 3 US laboratories and CERN: • BNL – • Tooling design - reaction, impregnation, shipping • Coil work - react, instrument and impregnate (50-50% BNL/ LBNL) • FNAL – • Magnetic cross-section design • Design and fabrication of all islands, end spacers and shoes • HQ magnet test and single coils mirror test • LBNL – • Coil winding, curing, reaction, instrumentation, impregnation. • Design, analysis and fabrication of structure • Magnet assembly and Test • Tooling design and fabrication • CERN • Test S. Caspi

  7. TQ-HQ Similarities and Differences • HQ • 120mm bore, 15mm cable • 15T + alignment + field quality • keys bladders assembly • Al shell • Axial Al rods • +Al collars + alignment keys • + layer 1 TQ- (shell/Collar) C/S* • 90mm bore, 10mm cable • Peak field 13T, no alignment • Keys & bladders / press assembly • Az. pre-stress - SS shell / Al shell • Axial load - end plates / Al rods • Pads without alignment • Protection heaters – layer 2 only *C is collar structure S is shell structure S. Caspi

  8. HQ Progress 2008 June Presented conceptual designs for 114 and 134 mm bore July Selection of 120 mm quadrupole aperture for Phase 1 Sept. Cable and coil cross-section geometry finalized Dec. All coil fabrication tooling in procurement 2009 Mar. All coil and structure components in procurement Apr. Cables for ~10 coils fabricated (54/61 and 108/127) Sept. Coil 1 completed and coil 2 wound Dec. Coil 2 completed, coil 3-4 reacted, coil 5 wound 2010 Jan. Structure pre-assembly completed Feb Coil 1-4 completed Mar Assembly completed Apr. HQ01a test coils 1-4  results June HQ01b test coils 1,4,5,6  results Present Aug. Coils 1-9 completed, 10 underway Dec 12 coils completed and 3-4 tests S. Caspi

  9. HQ Parameters S. Caspi 10/28/2019

  10. HQ - Coil S. Caspi

  11. HQ – Alignment Keys Alignment keys for field quality 10/28/2019 S. Caspi

  12. HQ – Aluminum Collars • Assemble the coils, • Displace the yoke to reduce saturation effects S. Caspi

  13. HQ – Iron Pads Iron pads complete the coil subassembly 10/28/2019 S. Caspi

  14. Merging two subassemblies Coil subassembly is placed within the structure subassembly 10/28/2019 S. Caspi

  15. Final Assembly and Pre-stress Four “Masters” are used to align and pre-stress the two subassemblies during the key and bladder operation 10/28/2019 S. Caspi

  16. LARP – HQ Cross-Section • 0.8 mm strand • 15 mm wide cable • 120 mm bore • 4.4 K/1.9 K -195/214 T/m • 4.4 K/1.9 K – 13.7/14.9 T S. Caspi

  17. Room temperature before loading S. Caspi 10/28/2019

  18. Bladder operation Gap opening between load key and pad master * Large scale factor to simulate displacements S. Caspi 10/28/2019

  19. Key insertion Shimming of the load key with 600 mm stainless steel shims * Large scale factor to simulate displacements S. Caspi 10/28/2019

  20. Cool-down DR of 270 mm * Large scale factor to simulate displacements S. Caspi 10/28/2019

  21. With Lorentz forces at 219 T/m DR of 78 mm * Large scale factor to simulate displacements S. Caspi 10/28/2019

  22. ANSYS 3D Analysis • Axial pre-load • Azimuthal pre-load • Cool-down • Excitation Low pre-stress during assembly Cool-down and high pre-stress No stress overshoot Reusable structural components S. Caspi 10/28/2019

  23. HQ - Average Azimuthal Stress Average stress in HQ is 140 MPa but local stress expected to exceeds 200 MPa TQS performed above 90% , 150 MPa average stress and over 200 MPa local stress MPa -212 -188 -164 -140 -116 -92 -68 R=120 mm -44 R=90 mm -20 10/28/2019 S. Caspi

  24. Coil Preparation and Fabrication CAD Rapid Prototyping (RP) Wire EDM 10/28/2019 S. Caspi

  25. Winding and Curing Coil Winding Curing Cured Layer 1 S. Caspi

  26. Reaction Tooling • 72 hr at 210 C • 48 hr at 400 C • 48 hr at 665 C Post Reaction: NbTi Leads, VT, SG. Iimpregnation Tooling 10/28/2019 S. Caspi

  27. Impregnated Coil (PC1) 10/28/2019 S. Caspi

  28. Coils Assembly and Alignment Alignment Keys Coil & heater Collars S. Caspi

  29. HQ01a – ready to test Aluminum shell + strain-gages S. Caspi

  30. HQ01a Measured Stress S. Caspi 10/28/2019

  31. HQ01a/b performance HQ01a Q1 - 12183A (141T/m, 71% of ss) Q11 - 13683A (157T/m, 79% of ss) HQ01b Q1 - 13308A (153T/m, 77% of ss) HQ01a - all quenches in coil #3 S. Caspi 10/28/2019

  32. HQ01b Training at 4.4K Linear behavior of coils azimuthal stress versus shell Linear behavior of coils azimuthal stress with current square S. Caspi

  33. Voltage Activity During a Quenchand an Impulse Test Protection heaters fire Voltage Breakdown Voltage Impulse test on a damaged coil showing arcing activity S. Caspi 10/28/2019

  34. HQ01a Test – Coil #2 • Although Coil #2 never quenched visual damage is seen on the outer layer from to island S. Caspi 10/28/2019 34

  35. HQ01b Test – Coil #6 • Voltage breakdown at the return-end of coil #6 between next to shoes. • This location exhibits the highest voltage difference within a coil as well as high risk location when both layers and both shoes meet at one spot. Top view Side view S. Caspi 10/28/2019 35

  36. HQ End Potential hazards are nesting outer blocks and local convergence of the outer most turns of both layers and their shoes. S. Caspi

  37. Impulse Tests on HQ Coils • Coils #1,2,3,4,5,7 went through an impulse test (#6 was cut) • Coils #1,3,5,7 passed • Coil #2,4 failed • Coils for HQ01c test • Use coils #1,3,5,7. Since coil #3 was a limiting coil during HQ01a it is conceivably it will limit the magnet plateau. • The test is to confirm detection of inter-coil high voltage risks S. Caspi

  38. Coil1 Coil4 10ms Coil5 Coil7

  39. Coil 3 Whole coil voltage at the start of ramping. Vmax = 110V Coil 3 Whole coil voltage at the end of ramping. Vmax = 1100V

  40. Full ramping on coil 4 Higher peaks indicate arcing Abnormal drop 1 second

  41. First instance of arcing in coil 4 10ms S. Caspi

  42. Full ramping on coil 2 Higher peaks indicate arcing

  43. Coil 2 Whole coil voltage at the start of ramping. Vmax = 105V Coil 2 Whole coil voltage at the end of ramping. Vmax ~ 650V

  44. Coil 2 Arcing Zoom-in

  45. Future Impulse Tests • BNL/FNAL/LBNL start doing impulse tests • Impulse test on previous TQ/LQ coils • Impulse tests involve risks, short pulses do not remove the risk. S. Caspi

  46. HQ Summary • A 120 mm bore, Nb3Sn quadrupole is under construction and testing • The magnet is optimized for alignment and field quality • Magnet is expected to reach ~215 T/m at 1.9 K • The first tests of HQ01a/b achieved expected mechanical performance and intermediate gradients of 153-157T/m • Performance overshadowed by voltage breakdown in end-regions . • Need to re-evaluate risks - reduce hi-pot voltage, increase layer-to-layer and coils-to-shoes insulation, add voltage impulse tests • The next test, HQ01c – verify magnet performance with coils that passed voltage impulse tests (#1,3,5,7). S. Caspi

More Related