Risk Surveys

Risk Surveys. Lean Six Sigma Storybook. So what is a Risk Survey?. Project Charter. Problem Statement Anecdotal evidence suggested that the turnaround of Risk Surveys was up to; 10 months for new business, 12-18 months for renewals This was due to a substantial backlog. .

taber
Download Presentation

Risk Surveys

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Surveys Lean Six Sigma Storybook

  2. So what is a Risk Survey?

  3. Project Charter Problem Statement Anecdotal evidence suggested that the turnaround of Risk Surveys was up to; 10 months for new business, 12-18 months for renewals This was due to a substantial backlog.

  4. Project Charter Project Goal: To reduce the completed Risk Survey Report cycle time and ensure that 90% are processed within the turnaround targets of 10 days for new business, 30 days for renewals and

  5. Project Charter Project Constraints:. Project Scope: In Scope: All Risk Surveys Out of Scope: The Underwriting function Branch Processes

  6. Process Map of the current process In Scope

  7. Voice of Customer Matrix

  8. Lean Six Sigma Fundamentals

  9. Data Collection Plan

  10. Baseline Data - Completed Surveys Time (Days) Taken to Complete Surveys • Sept 2010 • 567 days or 19 months - The greatest time taken to complete a Re Survey. • Sept 2010 • 595 days or 20 months - The greatest time taken to complete a New Survey. • Currently 97% defect rate New Survey goal of 10 days is about here. Everything to the right of the red line is a defect. Re Survey goal of 30 days is about here. Everything to the right of the red line is a defect.

  11. Value Stream Map of the Process

  12. Lean Six Sigma Fundamentals

  13. Potential Root Causes

  14. Improvement Workshop

  15. Lean Six Sigma Fundamentals

  16. Survey Report Forms • The Risk Survey report forms have been modified. The new versions capture slightly less info than previously, but require 30% less time to produce.

  17. Visual Controls Example of map showing outstanding requests from a 6 week period in the Auckland Area. Each Surveyor has a different colour

  18. Visual Controls Map zoomed in on requests from East Auckland showing multiple requests allocated to different surveyors. These can now be allocated to just one surveyor, thus saving travel time and cost.

  19. Lean Six Sigma Fundamentals

  20. Controls – Risk Survey Dashboard The Dashboard is shared between the Risk Survey Team and Branches to allow better communication of Surveyor work in progress and resource availability

  21. Controls – Results so far • Average time to complete surveys has fallen by 33% in last 4 months (based on sample timings taken in August ’10 vs timing taken in Dec ’10). • The Range has also decreased significantly The average completion time has fallen from here to here Back in July 10 the range (highest minus lowest) was 4 ½ hours The range now is at 2 ½ hours