1. SW Oregon Coast Reinforcement Project Anthony Radcliff
Transmission Planning
Bonneville Power Administration
2. Background The southwest Oregon load service area extends from Fairview to Brookings, serving the City of Bandon, Coos Currey, and PAC’s Isthmus and Coquille feeders.
The area is served by two 230kV and one 115kV lines from Alvey, Dixonville, and Reedsport respectively.
The loads served south of Fairview are served with looped service via a 230kV line from Fairview to Rogue and a 115kV line from Bandon to Rogue.
3. Challenges The weakest portion of the system are both radial lines served from Rogue down the southern Oregon coast to Brookings and Harbor on Coos Currey’s system.
The southern Oregon coast is a winter peaking system with the worst contingency being the loss of the Fairview-Rogue 230kV line.
The contingency possibly causes voltage instability, depending on the load level, rather than thermal limit overloads.
Previous studies recommended constructing a 46 mile long 115kV from Bandon to Rogue to mitigate the voltage instability problems.
4. South of Fairview Service Area
5. Reactive Power Margin Bottom of the QV Curve = 4MVARs
90% voltage = 1MVAR
Initial point violates BPA’s voltage criteria
Maximum switch-able (8% voltage swing) = 7MVARs….too small!
6. Original Plan of Service: Transmission Line New 46 mile long Bandon-Rogue 115kV line constructed to 230kV specification for later upgrade
1.1in ACSRTW Rogue conductor was chosen
Initial estimates:
Line, Towers, etc… = $25M plus
Land/Environmental Survey = $3.6M
Land/New right of way = $$$$$
Performance
Line could be put into service between 2008-2010
Voltage support would be needed by the 2015 predicted load level
Options available at that time:
Upgrade to 230kV
Requires transformer at Bandon ($5M-$7M)
SVC at Rogue
Only small amounts of reactive can be switched without large voltage changes
7. Other Considerations on the New Transmission Line Light loading conditions
Area experiences high voltages under light loading conditions that may damage equipment
Adding another line may aggravate high voltages
The new line will place other lines below their surge impedance loading, causing them to produce more reactive power than they absorb
More available reactive power will boost voltages
Area is under light loading conditions most of the time
Conductor size
A larger conductor than necessary (thermal loading) was specified due to the voltage support required
Adds to the cost of the project
8. Other Options Considered The drawbacks of the new line project caused another round of studies aimed at finding a non-transmission line solution
Main deterrent was price…. $35M to $45M
Other options:
Multiple switched shunt capacitor groups
Would require many due to switching sensitivities and coordination would be difficult
Series capacitors
Tapped transmission line would make placement difficult due to voltage profile caused by series capacitor group
Short transmission lines (distance in km should exceed voltage in kV)
Static VAR Compensator (SVC)
Continuous reactive power output (switching sensitivities no longer a problem)
Can mitigate light loading/high voltage issues
Supports voltages to the predicted 2016 load level, outperforming the transmission line
The next limitation on the system is the thermal limit of the Bandon-Rogue 115kV line
9. Static VAR Compensator The Static VAR Compensator (SVC) became Planning’s preferred plan of service of the alternates to the new transmission line.
SVC Specification:
40MVARs inductive/45MVARs capacitive
Initial estimate for a turnkey device was $5M
An additional $2M in site development, communications, and high voltage connections
Pros
Solves voltage instability issue
Delays new line construction nine years
Cost less than a new transmission line
Mitigates high voltage issues
Could be on-line in 14 months
Cons
Maintenance: cooling systems, remote location, and untrained personnel
New line may be required in the future
The studies showed that if the load continued to grow, both projects would be needed eventually
10. Factors Considered in Project Selection Matrix Team
A group of BPA employees consisting of engineers and financial analyst assigned to evaluate projects and give their recommendation to management
Risk mapping
Financial Agency Target
Legal Impacts
Environmental
External Stakeholders
People and Processes
Reliability
Each area is graded on severity of impact
Can be used to compare competing projects
The line and the SVC would score the same in most categories except Financial Agency Target and Environmental impacts
New line cost considerably more and would require land in possibly sensitive areas
11. South Oregon Coast
12. Geographical Map
13. System Map
14. South of Fairview Service Area
15. System One Line
16. Project Timeline By Need Date