Moog Components Group: Team 26. Team Members: Andrew Adams, Jeff Janiak , Danny Sasso and Jae Oh Faculty Advisor: Dr. Shewchuk. Moog Components Group/Guardian. Formerly Poly-Scientific; Purchased by Moog in 2003 Headquartered in Blacksburg, Virginia
E N D
Moog Components Group: Team 26 Team Members: Andrew Adams, Jeff Janiak, Danny Sasso and Jae Oh Faculty Advisor: Dr. Shewchuk
Moog Components Group/Guardian • Formerly Poly-Scientific; Purchased by Moog in 2003 • Headquartered in Blacksburg, Virginia • Designed to track and jam incoming ground based missiles
Project Goals • Increase throughput • Improve operation efficiency • Improve on-time shipments
Current Setup • 4 workers • Independent Cells • Component most complete has precedence
Problem Statement • Running same setup for over 5 years • Continuous increase in demand • Challenge: To accommodate for the increases in demand and large amounts of overtime and inventory that have accumulated.
Project ApproachData & Analysis • Process Times • Process Time Sheet • Employee Questioning • Scheduling Method • Process Steps • Production Sheet • Production Schedule • Put picture of Process sheet or Production Sheet
Project ApproachDeliverable Decision • Rockwell Arena Simulation • Already used by MOOG • Will give client • Worker Utilization • Unit output quantity • Time in system • Client can customize • Worker Schedule • Weekly Production Amounts • Process times
Project ApproachModel Creation & Examination • Created Current Setup • Performed Hypothesis Test • Created Alternative models • Reviewed output data and check financial viability • Put Hypothesis test calculation here
Alternative Designs • Purchase of new equipment • Allows department to bypass largest contributor of time distribution • Considerable investment • Job shop • No costs involved • Job shop/New equipment setup • One queue for all workers • Additional worker • Simplest improvement • Quickest to implement
Simulation Results • Purchase of new equipment • 25% increase in production • 87% worker utilization • Job Shop • 12.5% increase in production • 81% worker utilization • Job Shop/New equipment • 37.5% increase in production • 90% worker utilization • New hire or internal transfer • 31.25% increase in production • 69% worker utilization
Recommended Alternative • Job Shop/New equipment
Comparison • Current • 16 units/week • $104000 in revenue/week • 1580 avg. time in system • Equipment shared facility wide • Job Shop/New equip. • 22 units/week • $143000 in revenue/week • 1450 avg. time in system • Dedicated equipment
Project Benefits • Increased production rates • Less WIP • Increased due date success • Allows for future growth
Project Management • Weekly Team Meetings • Members assigned tasks to perform between meetings • Worked as teams on certain tasks
Summary & Acknowledgements • Instructor: Dr. Kleiner • Faculty Advisor: Dr. Shewchuk • Moog Contacts: Eric Alsup, Wiley Hagy • Moog production operators • Dr. Pasupathy & Susan Hunter for Arena consultation