CAPITOL COMPLEX MULTIPLE PROJECT UPDATE. Overview of Scheduled Capitol Complex Projects Review of Various Projects Locations Scopes of Work Construction Sequencing & Operational Impact. OBJECTIVES. Scheduled Capitol Complex Projects.
E N D
Overview of Scheduled Capitol Complex Projects • Review of Various Projects • Locations • Scopes of Work • Construction Sequencing & Operational Impact OBJECTIVES
FORUM BUILDINGRestroom RenovationsRoofing & Rain Leader ReplacementAuditorium UpgradesSite Upgrades Scope of Work • Renovations to the existing restrooms & adding three new at the auditorium corridor. • Redirect the existing rain leaders & abandon the existing in place. • Install new rubber roofing. • Replace existing auditorium seating and floor finishes. • Repair pot holes at the entrance drive to the auditorium. • Replace the concrete ramps that access the Ground Level. • Partial sidewalk replacement.
FINANCE BUILDINGRestroom RenovationsRoof Replacement & Repair of Rainwater Leaders Scope of Work • Renovation the existing public restrooms. • Line the existing rain leaders with an epoxy reinforced resin. • Install new rubber roofing. • Sidewalk replacement.
RYAN BUILDINGRenovations to Skylights, Roof & Windows Scope of Work • Replace the main Skylight. • Repair roof flashings and roof drains. • Refurbish the exterior of the existing windows.
EAST WING of CAPITOL BUILDINGRenovations/Improvements Scope of Work • Remove/reinstall the granite pavers and stair treads at the Plaza. • Demolition/removal of all existing roofing and landscaping. • Install new roofing, plantings and irrigation. • Repair Skylights • Refurbish lollipop light fixtures with LED lighting. • Refurbish the existing fountains.
East Wing Fountain Part of Second & Third Sequences