Christ the King Catholic Church Addition 1599 Tunner Drive, Courtenay, BC Board Presentation – 09 September 02008. Conceptual Design Meeting No. 08 Review previous conceptual work; Review latest conceptual design work; Concept Design Discussion; Next Steps;.
E N D
Christ the King Catholic Church Addition 09 September 02008 Christ the King Catholic Church Addition 1599 Tunner Drive, Courtenay, BC Board Presentation – 09 September 02008
Christ the King Catholic Church Addition 09 September 02008 • Conceptual Design Meeting No. 08 • Review previous conceptual work; • Review latest conceptual design work; • Concept Design Discussion; • Next Steps;
Christ the King Catholic Church Addition 09 September 02008 • New Conceptual Designs “J & K” • Challenge; • Use vaulted ceiling option • Create a better entrance • Two Entry Options • Slot entry • Side entry
Christ the King Catholic Church Addition 09 September 02008 • New Conceptual Designs “J & K” • After brief design meeting; • Preferred Option K • Side entry
Christ the King Catholic Church Addition 09 September 02008 LOWER FLOOR LEVEL
Christ the King Catholic Church Addition 09 September 02008 • UPPER • FLOOR • LEVEL • ENTRANCE WIDENING RENOVATIONS TO BE DONE AFTER ADDITION COMPLETED • - NEW ELEVATOR INSTALLED IN LOCATION OF EXISTING STAIR WELL AFTER ADDITION COMPLETED
Christ the King Catholic Church Addition 09 September 02008 Concept Evaluation:
Christ the King Catholic Church Addition 09 September 02008 Concept Cost:
Christ the King Catholic Church Addition 09 September 02008 • Next Steps: • Determine Preferred Concept; • Prepare presentation package;