Asset Information. LG&E & KU. LG&E – KU Service Territory. LG&E-KU Divisions. There are 3 main divisions in LG&E-KU Energy Delivery Gas & Electric Distribution (pipes & wires) Gas Transmission Meter Reading Revenue Collection Electric Transmission Energy Services (Power Generation).
E N D
Asset Information LG&E & KU
LG&E-KU Divisions • There are 3 main divisions in LG&E-KU • Energy Delivery • Gas & Electric Distribution (pipes & wires) • Gas Transmission • Meter Reading • Revenue Collection • Electric Transmission • Energy Services (Power Generation)
Statistics • Customers by Utility • LG&E Gas Customers – 318,000 • LG&E Electric Customers – 394,000 • KU Electric Customers – 540,000 • Gas Distribution • 4,300 miles • Gas Transmission • 5 UG Storage Fields • 12 Interconnects with Texas & Tennessee Pipelines • 2 Compressor Stations • Electric Distribution • Conductor miles – 39,000 • Substations - 600
Asset Information’s Role • Map existing facilities and attributes that are important to crews, internal & external clients and interface to other applications • Provide • Prints f • SpecialtyMaps • Provide Supporting Documentation • Report to internal & external clients • Team Leaders, Managers & Senior Management • PSC & DOT • Benchmarking Studies • Tax Department • Scan & Store Records for Future Verification of Facilities
Asset Information’s Facility Records Technician • Locations • Louisville • Lexington • Danville • Pineville • Earlington
Asset Information’s Mapping Roles • Gas – LG&E • Distribution & Transmission Mains & Services • Valves • Regulation Facilities • Electric – LG&E & KU • Distribution Poles, Wires, Transformers • Operating Devices (switch Gears, switches, fuses) • Substations (including internal worlds) • Lights – LG&E & KU • Light type, Wattage, Customer Name, Location • Landbase – LG&E & KU • Correct or reposition existing road R/W’s & Street Names • Labeling all tributaries • Placing Easements, Building Footprints in HCA’s, Taxing Districts, etc. • Place new Subdivisions or Roads from Dedicated Plats
Connectivity • LG&E Gas – 99.3% • LG&E Electric – 98.8% • KU Electric – 98.9%
Best Practices • Annually personnel come together across state • Employees are assigned mapping procedures for…. • Landbase • Gas • Electric • Lights • Mapping procedures are presented, discussed & a decision on what the “best practice” is for mapping the particular facility moving forward
Wrap up • Asset Information – LG&E and KU • Map all facilities that need to be reported on, data is needed for field personnel or is needed for interfacing with other applications • Provide information about existing facilities to internal and external customers • The GIS system interfaces with several applications i.e. • OMS, CCS, WMS, FieldSmart, DETS, RAPP, SynerGEE, IRAS, Bass-Trigon, FIM, Gas Leak Manager, etc. • Important • Communicate & work together (especially field personnel) • Quality over quantity