1 / 14

PEDDIE AND WESLEY AREA REINFORCEMENT

STRENGTHENING / RELIABILITY PROJECT. PEDDIE AND WESLEY AREA REINFORCEMENT. Compiled by: Simphiwe Dlulane Tel: - 043 – 743 2750 Email: DlulanS@eskom.co.za Nondumiso Mahlaba Tel : - 033 395 3722 Email: mahlabnl@eskom.co.za. PURPOSE OF PRESENTATION.

tanaya
Download Presentation

PEDDIE AND WESLEY AREA REINFORCEMENT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STRENGTHENING / RELIABILITY PROJECT PEDDIE AND WESLEY AREA REINFORCEMENT Compiled by: Simphiwe Dlulane Tel: - 043 – 743 2750 Email: DlulanS@eskom.co.za Nondumiso Mahlaba Tel: - 033 395 3722 Email: mahlabnl@eskom.co.za

  2. PURPOSE OF PRESENTATION • Request support to strengthen the 22kV networks in the Peddie and Wesley areas as well as improve the reliability of supply to customers in this area. This project entails building 4 x 22kV feeder bays, installing 2 x 22kV voltage regulators and constructing 22kV link lines. • Project cost estimate (2011/12 Rands): R 15 650 000

  3. BACKGROUND INFORMATION • Peddie substation is a 66/22kV 1x10MVA substation which supplies 2 feeders, Peddie - Craighead 22kV line (with a maximum demand of 2.9MVA, 4079 customers and 32km long ) and Peddie - Wesley 22kV line (with a maximum demand of 4.5MVA, 4918 customers and 192km long). • Wesley substation is a 66/22kV 2x10MVA substation which supplies 2 feeders, Wesley - Peddie 22kV line (with a maximum demand of 2.9MVA, 6529 customers and 171km long) and Wesley – Hamburg 22kV line (with a maximum demand of 2.5MVA, 10066 customers and 139km long). • These networks have the network class of C2 by default. Reliability gate keepers have the limit of ≤ 220km line length and ≤5000 customer base. The mainline of these feeders consist of Hare conductor except for Peddie - Wesley 22kV line which consists of Mink conductor.

  4. Geographical Layout of Peddie & Wesley substation supply zones Craighead fdr Peddie SS Wesley fdr Hamburg fdr Wesley SS Peddie fdr

  5. PROBLEM STATEMENT • The Peddie – Craighead and Wesley – Hamburg 22kV feeders are experiencing low voltages. • The Peddie and Wesley Substations distribution networks do not meet the regional reliability guide in terms of customer numbers. • Peddie – Wesley 22kV feeder forms part of the 2008/9 SR underperforming pareto MV feeders.

  6. Build a 22kV feeder bay at Peddie S/S and construct ±600m Hare line to structure NDH-2 • Create normally open point at structure NDH-1 • Build a 22kV feeder bay at Wesley S/S and construct ±4.6km Oak line to structure 2PED-WES-327 • Create normaly open point at structure 2PED-WES-329 • Build ±6km Pine link line from WES27-13 to NJO106-2 • Create normally open point at structure ZWE55 • Build a 22kV feeder bay at Wesley S/S and construct ±4.8km Oak line to structure TUK 2 • Create normally open point at structureTUK 1 • Build a 22kV feeder bay at Peddie S/S and construct ±10.4km Hare line to structure CHD-PED-86 • Create normally open point at structure CHD-PED-85 • Build ±4.1km Mink link line from LMAF005-31 to LMBG004-28 • Create normally open point at structure LMAG008-100 • Install a Voltage Regulator at structureLMVD013-2 • Build ±3km Mink link line from X-PHA-77 to LMBK006-94 • Create normally open point at structure X-PHA-37 • Install a Voltage Regulator at structure LMAG008-75 • Solution 1 (Preferred) Network reconfiguration and voltage regulators LMAF005-31 CHD-PED-86 LMBG004-28 NEW NOP NDH-2 NEW NOP NDH-1 LMBK006-94 X-PHA-77 NEW NOP NEW NOP TUK2 NJO106-2 NEW NOP 2PED-WES-327 WES27-13 NEW NOP Fish River Sun Hamburg Peddie S/S LMAG008-97 2PED-WES-5 CHD-PED-83 NOP Wesley S/S PED-WES-FR-T-118 2PED-WES-331 WES-HBG-16 COST ESTIMATE (2011/12 Rands): R 15 650 000 NPV: R 4,825 457.00 MIRR: 14.70%

  7. Geographical Layout after completion of Solution 1 Naudeshoek Craighead Dube Peddie SS Wesley Hamburg Tuku Wesley SS Peddie Fish River

  8. MV NETWORKS AFTER COMPLETION OF SOLUTION 1

  9. Solution 2: Build a new Ndusi 132/22kV 1x10MVA Substation Build 10km of 22kV Hare line to interconnect with Wesley/Hamburg 22kV feeder at MMDJ012/12. Create a normally open point at structure P41/99. Build approximately 15km of 132kV Wolf line from Peddie substation to a proposed site for the new Ndusi substation. Install 1x132kV feeder bay, 132/22kV 10MVA trfr and 3x22kV feeder bays. Craighead Naudeshoek Build 3km of 22kV Hare line to interconnect with Peddie/Craighead 22kV feeder at structure LM AG008/10. Create a normally open point at LMAG008/1. Build a 22kV feeder bay at Peddie S/S and construct ±600m 22kV Hare line to structure NDH-2 of Peddie/Wesley 22kV feeder. Create NOP at NDH-1 to split the Peddie/Wesley 22kV line into Peddie/Wesley & Peddie/Naudeshoek 22kV feeders. Dube Peddie SS Tuku Wesley Build 6km of 22kV Hare line to interconnect with Wesley/Peddie 22kV feeder at WES132/29. Create a normally open point at 2PED/WES/238. Hamburg Ndusi SS Wesley SS Peddie Peddie Peddie Fish River Fish River Fish River COST ESTIMATE (2011/12 Rands): R 30 000 000 NPV: -R 5,873 514.00 MIRR: 11.70%

  10. MV NETWORKS AFTER COMPLETION OF SOLUTION 2

  11. IMPLICATIONS OF DOING NOTHING • The Peddie – Craighead and Wesley – Hamburg 22kV feeders will continue experiencing low voltages. • No spare capacity for future load demand • Poor reliability of supply (violating Planning Reliability Guideline)

  12. COST BENEFIT ANALYSIS

  13. RECOMMENDATION Implement Solution 1 as proposed • Build a 22kV feeder bay at Peddie S/S and construct ±600m Hare line to structure NDH-2 • Create a normally open point at structure NDH-1 • Build a 22kV feeder bay at Wesley S/S and construct ±4.6km Oak line to structure 2PED-WES-327 • Create a normally open point at structure 2PED-WES-329 • Build ±6km Pine link line from structure WES27-13 to structure NJO106-2 • Create a normally open point at structure ZWE55 • Build a 22kV feeder bay at Wesley S/S and construct ±4.8km Oak line to structure TUK 2 • Create a normally open point at structure TUK 1 • Build a 22kV feeder bay at Peddie S/S and construct ±10.4km Hare line to structure CHD-PED-86 • Create a normally open point at structure CHD-PED-85 • Build ±4.1km Mink link line from structure LMAF005-31 to structure LMBG004-28 • Create a normally open point at structure LMAG008-100 • Install a Voltage Regulator at structure LMVD013-2 • Build ±3km Mink link line from structure X-PHA-77 to structure LMBK006-94 • Create a normally open point at structure X-PHA-37 • Install a Voltage Regulator at structure LMAG008-75 PROJECT COMPLETION DATE: 31/12/2012 TOTAL PROJECT COST (2011/12 Rands): R 15.6 mil

  14. END Thank you

More Related