1 / 16

SPS Removal and Reconfiguration Planning for LS2

Detailed overview of activities for removal, reinstallation, and refurbishment in the SPS for LS2, including coordination team info and key tasks. Access complete planning at the shared link.

Download Presentation

SPS Removal and Reconfiguration Planning for LS2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPS 1 and 5 during LS2Focus on Point 1 J.MEIGNAN EN-ACE-OSS 31/10/2018

  2. Before we start • My planning is available here: https://cern.sharepoint.com/sites/Projects-Accelerator-Complex-Schedules/default.aspx • Main SBDS tasks reported in the main planning (David), details are available in my planning J.MEIGNAN

  3. SPS closure (chain1): 21/09/2020 Access SPS, except LSS1-2: 14/01/2019 Access LSS1-2: 01/07/2019 J.MEIGNAN

  4. Beam dump main activities • Removal of the dumps • Removal of the beam line • Cabling campaign in LSS1 • ABT racks reconfiguration • Re-installation of the beam line • Warning: floor refurbishment J.MEIGNAN

  5. Beam dump main activities • Removal of the dumps • Removal of the beam line • ABT racks reconfiguration • Re-installation of the beam line • Warning: floor refurbishment J.MEIGNAN

  6. Removal of the dumps in LSS1 • Five equipmentsto be removed • TIDVG • TFDG • TIDH • TFDH + Vacuum chamber VKNW.11871 • TIDVG shielding J.MEIGNAN

  7. Removal of the dumps in LSS1 LSS1 situation at the beginning of LS2 J.MEIGNAN

  8. Removal of the dumps in LSS1 TIDVG removal J.MEIGNAN

  9. Removal of the dumps in LSS1 TFDV + vacuum chamber removal J.MEIGNAN

  10. Removal of the dumps in LSS1 TIDH removal J.MEIGNAN

  11. Removal of the dumps in LSS1 TFDH removal • Removal of the TIDVG shielding. • Do we need to move these equipment? • Vacuum pump • Vacuum valve • MDVA J.MEIGNAN

  12. Where are they going? • Two options: • BA3 • BA6 • Under discussion (RP purpose/ Storage place/ road crossing) • Transport performed when nobody is in the tunnel (early morning or late afternoon) Go to storage in Prevessin Go to storage in Meyrin J.MEIGNAN

  13. Floor refurbishment in LSS1 • 2 zones damaged (transport side) near to TIDH and TIDVG No passage in LSS1 during the works (1 week) No VEHICLES in LSS1 (only pedestrians) J.MEIGNAN

  14. What we still need for point 1? • Verify the coactivity in LSS1 (beginning 2020) • Access during PPS upgrade (May 2019): guard? • The dates of your VICs J.MEIGNAN

  15. SPS COORDINATION • David Mcfarlane 164247 (SPS coordinator) • Franck Bais 165467 (SPS Worksite supervisor) • SPS-SBDS COORDINATION TEAM • Antonio Grande 162721 (For beam line activities and VSC resources optimization) • Jonathan Meignan 164026 (For activities in SPS1 and SPS5 – including SBDS) J.MEIGNAN

  16. Any questions?