Casino Facility Progress Report

Casino Facility Progress Report. Construction Progress – February 1, 2012. Arial View. January 26, 2012 Tour. Team member Training Room. January 26, 2012 Tour – Team Member Dining Room. January 26, 2012 Tour – Epic Buffet. January 26, 2012 Tour – Gaming Floor.

tarak
Download Presentation

Casino Facility Progress Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Casino Facility Progress Report

  2. Construction Progress – February 1, 2012

  3. Arial View

  4. January 26, 2012 Tour • Team member Training Room.

  5. January 26, 2012 Tour – Team Member Dining Room

  6. January 26, 2012 Tour – Epic Buffet

  7. January 26, 2012 Tour – Gaming Floor

  8. Comparative Photos (Final Cut Steak & Seafood House – photo #1)

  9. Comparative Photos (Final Cut Steak & Seafood House – photo #2)

  10. Comparative Photos (Epic Buffet)

  11. Comparative Photos (Skybox Restaurant & Bar)

  12. Comparative Photos (Serpentine Sign)

  13. Comparative Photos (Poker Room)

  14. Summary Timeline • Surveillance: • System Programming/Testing: January 3-15, 2012 • System Turnover to Property: January 16, 2012 • Food & Beverage: • Epic Buffet & Final Cut Steakhouse Partial Certificate of Occupancy: December 27, 2011 • Team Member Dining Room Open: January 6, 2012 • Slots: • Carpet Installation: December 14, 2011 to February 10, 2012 • Slot Bases Installation: December 19, 2011 to March 2, 2012 • Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval) • Estimated Installation: TBD (30 day duration) • Table Games: • Artwork/layouts submitted to Commission for review & approval: December 21, 2011 • Carpet Installation (Pit areas): To be completed by February 29, 2012 • Order/Delivery: All games ordered and ready to ship (awaiting final Commission approval) • Estimated Installation: March 1-5, 2012 • Final Inspection/Certificate of Occupancy: • Certificate of Occupancy: March 15, 2012

  15. Staffing Update • All employees identified as key employees to date have submitted a complete key license application (14 in total).

  16. Vendor Update

  17. Public Safety Outreach • Most recent meeting held on January 30, 2012 with the following attendees: • Captain Brad Weis – Toledo PD (Strategic Response – Hollywood Contact person for opening • Thomas Wiegand – Toledo PD (Area Commander) • Chief Mark Hetrick – Perrysburg Township PD • Chief Thomas Cairl – Northwood PD • John Altman – Ohio Highway Patrol • Eric Reynolds – Deputy Chief, Wood County • Seven (7) other members of local law enforcement • Topics included: Team member & guest safety, Traffic flow, Natural Disasters, Gangs, Miscellaneous crimes & threats. • Bi-weekly meetings to occur going forward.