Scheduling

MGMT 483 Week 8. Scheduling. Background. A schedule is the conversion of a project action plan into an operating timetable It serves as the basis for monitoring and controlling project activity One of the major project management tools Work changes daily so a detailed plan is essential

tasha
Download Presentation

Scheduling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MGMT 483 Week 8 Scheduling

  2. Background • A schedule is the conversion of a project action plan into an operating timetable • It serves as the basis for monitoring and controlling project activity • One of the major project management tools • Work changes daily so a detailed plan is essential • Not all activities on a project need to be scheduled to the same level of detail Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  3. Scheduling tools • Most scheduling is based on network diagrams • The diagram shows activity and event relationships and graphically portrays the sequential relationship between the tasks in a project • Clearly shows precedence – tasks that must come before or after other tasks Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  4. Network Scheduling Advantages • Consistent framework for planning, scheduling, monitoring and controlling the project • Shows interdependence of tasks • Shows when resources are needed • Ensures proper communication between parties to the project • Determines expected completion date • Identifies critical activities and those with slack Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  5. Network Scheduling Techniques • Around since the 1950s – 2 approaches initially • Critical Path Method (CPM) • Program Evaluation and Review Technique • Microsoft Project (and other software) have blended CPM and PERT into one approach Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  6. Terminology • Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete • Event - The result of completing one or more activities • Network - The combination of all activities and events that define a project • Drawn left-to-right • Connections represent predecessors Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  7. Terminology Continued • Path - A series of connected activities • Critical - An activity, event, or path which, if delayed, will delay the completion of the project • Critical Path - The path through the project where, if any activity is delayed, the project is delayed • There is always a critical path • There can be more than one critical path Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  8. Terminology Continued • Sequential Activities - One activity must be completed before the next one can begin • Parallel Activities - The activities can take place at the same time • Immediate Predecessor - That activity that must be completed just before a particular activity can begin Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  9. The two types of network diagrams • PERT / ADM: Activity on Arrow - Arrows represent activities while nodes stand for events • CPM / PDM: Activity on Node - Nodes stand for events and arrows show precedence Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  10. AON and AOA Format Figure 8-2 Figure 8-3 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  11. Constructing the Network (AON Version) • Begin with START activity • Add activities without precedents • There will always be one • May be more • Add activities that have those activities as precedents • Continue until all activities are added Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  12. Some practice • A simple example • Question 1 – page 374 • Question 7 – page 374 (do an AON diagram) Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  13. Microsoft Project AON Network Figure 8-12 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  14. Solving the Network Table 8-1 This table shows a simple project with 10 activities and their predecessors, plus 3 time estimates for completion of the activities. Draw the AON diagram – without the time estimates Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  15. The AON Network from Table 8.1 Figure 8-14 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  16. Calculating Activity Times Expected time • The next step is to calculate expected activity completion times from the data in Table 8-1 • a=optimistic time estimate • b=pessimistic time estimate • m=most likely time estimate Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  17. The Activity Expected Time Results Table 8-2 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  18. Critical Path and Time The nodes now show the activity, plus the Expected time, followed by the Variance Treating the expected times as certain - how long will it take to complete the project? What is the critical path – ie the longest path through the project Figure 8-15 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  19. The critical path • The project will take 43 days (this is the shortest time it can possibly take) • The critical path is a – d – j • If any of these activities take longer than the expected time, the project will be late Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  20. Critical path problem • Question 8 – page 375 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  21. Critical Path and Time – ES, EF, LS, and LF shown on the network diagram ES = Earliest Start EF = Earliest Finish LS = Latest Start LF = Latest Finish Figure 8-16 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  22. Slack • Slack (aka, Float) – In the previous section, the earliest possible dates for each activity were determined. • By starting the analysis at the end of the network and working through it backwards, the latest possible dates for each activity can be determined. • The difference between the early dates and the late dates is float or slack. • Activities on the critical path have zero float. Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  23. Slack Values Table 8-3 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  24. An example AON diagram showing ES, EF, LS,LF, slack and activity duration Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  25. Problem – calculating ES,EF, LS, LF, slack, and duration • Problem 19 on page 377 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  26. Precedence Diagramming • Precedence Diagramming – The Precedence Diagram Method allows for additional relationships to be established between activities. They are: • Finish to Start – The successor activity cannot begin until the predecessor finishes. This is the most common relationship depicted in networks. • Start to Start – The successor activity cannot begin until the predecessor begins. • Finish to Finish – The successor activity cannot finish until the predecessor activity finishes. • Start to Finish – The successor activity cannot finish until the predecessor activity starts. This relationship is rarely used. Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  27. Precedence Diagramming Conventions (MS Project) Figure 8-17 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  28. MS Project Gantt Chart version of the project described in Table 8-1 (page 344) Figure 8-18 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  29. Same data presented as an AON Network in MS Project Figure 8-19 Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  30. Uncertainty of Project Completion Time • The chance of completing a project within a given time period can be calculated. • The project activities are assumed to be statistically independent • The variance of a set of activities is equal to the sum of the variances of the individual activities • We are particularly interested in variances on the critical path Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.

  31. Uncertainty of Project Completion Time - example • The chance of meeting a particular project duration can be calculated as: D = the desired project completion time µ = the critical time of the project, the sum of the TEs for activities on the critical path = the variance of the critical path, the sum of the variances of activities on the critical path Z = the number of standard deviation of a normal distribution (the standard normal deviate) Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.