YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10. April 17, 2009. Overview. Yuba County Water Agency: Local sponsor Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to RD 784. Maximize federal funds by:

tass
Download Presentation

YUBA RIVER BASIN PROJECT Schedule and Cost Change Request (SACCR) CVFPB Agenda Item 10

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. YUBA RIVER BASIN PROJECTSchedule and Cost Change Request(SACCR)CVFPB Agenda Item 10 April 17, 2009

  2. Overview • Yuba County Water Agency: Local sponsor • Goal: Provide at least 300-year protection to the City of Marysville and 200-year protection to RD 784. • Maximize federal funds by: • Completing GRR • Secure credit from state & local expenditures as part of the TRLIA levee improvements • Defer non-Federal costs on Marysville until Congress Authorizes the GRR 1

  3. Project Elements • General Reevaluation Report (GRR) - RD 784 • Marysville Ring levee 2

  4. GRR Scope • Evaluate the Federal interest in reducing the risk of flooding in RD 784 • Alternatives to include the TRLIA Program, and additional alternatives that provide greater and lesser levels of protection for the area • GRR will establish the eligible credit from the TRLIA work that can be used towards Marysville or additional improvements in RD 784 3

  5. Why the GRR Scope Increased • We Learned a lot from the 1997 Flood Event • 1998 FS did not identify a need for work on the Lower Feather, Bear & WPIC Levees for 200-year protection • After the 1997 Flood Event • New underseepage guidelines required more work to achieve a given level of protection • Revisions to hydrology • The DWR Floodplain Mapping Study (Early 2000s) • Identified FEMA deficiencies in RD 784 • Lower RD 784 freeboard deficiency • Yuba River left bank stability problem 4

  6. Brief History of the GRR • Reclamation Board Increased the GRR Scope and Cost in 2004 – LRR Increased to a GRR • Corps has Requested Scope and Schedule Revision (2) to cover: • Sunk Costs > $8M • Additional Design Fees, Field Work, and Modeling • Additional Evaluation of Ecosystem Restoration, Environmental Data and In-House Labor Details Included in Board Package 5

  7. GRR Schedule • Alternative Formulation Briefing – July, 2009 • F6 Public Review (Draft EIS) – October, 2009 • Chief of Engineers Report – June, 2010 6

  8. Marysville Ring Levee • Strengthen 7.5 miles of levees • $50M estimate • 65% Federal: $32M • 35% Non-Federal: $18M • State: $12.6M • Local Share: $5.4M • 2008 Corps approval of Ring Levee as a “Separable Element” (OK to Begin construction while GRR is underway) 7

  9. Marysville Strategy • Begin construction – no delay or risk from the GRR (separable element) • Secure adequate appropriations • Minimize State/local cost-share: 1. Section 103(l) cost-share deferral, Corps Approval on April 3, 2009 (There is still a Non-Federal 5% cash requirement) 2. Secure credits from TRLIA and RD 784 for the local cost-share 8

  10. Marysville Schedule • Engineering Documentation Report (EDR) - Aug 2009 • Project Partnership Agreement – (PPA) - Nov 2009 • Award First Construction Contract – Apr 2010 9

  11. Requested Action 1.0 Approve Corps SACCR dated March 19, 2009 to increase costs by $10,500,000. 2.0 Amend the LDA with YCWA to increase the total agreement costs. 3.0 Amend the DA with the Corps to increase the total agreement costs. Approval Will: • Allow planning/design efforts to continue on both the GRR and Marysville Levee • Avoid additional schedule delays to the GRR and Marysville construction 10

  12. Thank You 11