Thrdplace Social Networking. Remote Team Member. Test Plan and Cases. Gaurav Doon. Testing Overview. Type of testing : system level acceptance test of the Thrdplace Social Networking project. Purpose of testing: verify the requirements captured in Winbook .
E N D
Test Plan andCases GauravDoon
TestingOverview • Type of testing:system level acceptance test of the Thrdplace Social Networking project. • Purpose of testing:verify therequirements captured in Winbook. • Scope of testing: include all capabilities and level of service requirements. • Focus of testing: testing will focus on use cases corresponding withwin conditions captured in Winbook. 4
Strong Points • We are good at sharing our vision. • We agree on a decision only after consulting everyone in the team and when everyone is satisfied with it. • Familiarity with technologies like MySql and HTML 5 which are used in the project will make things easier.
Weak Points • Due to clash of schedules, sometimes it becomes difficult to organize a team meeting. • Some technologies like PHP, thrdplace database are not known to the team members, but they will be implemented in the project.
Overall Project Evaluation • Atpresent,allthewinconditionshavebeendesignedandprototyped. • Initially,slowprogressandinconsistency betweenprototypeandwinconditions. • Adjustquicklyandcooperatewithclientscloselytocompleteaseriesofdifficultytasks,includingdatabasedesignandpopulation,influencemoduleimplementation,searchengineimplementation,recommendationsystemimplantation.
Operational Concept Description YixiangLiu
System Purpose • Thrdplace.comis a venue for fund-raising, resource sharing and commerce. • OursystemisasubsystemofThrdplace.com. • Oursystemisdesignedtoprovidesearch,rankingandrecommendationfunctionstoprojectcreatorsandcontributorsonThrdplace.com.
Prototype FengWen
SearchEngine • WeuseApache Solrfull-textsearchenginetosearchfor projectsor contributors fromthrdPlace.comdatabase.Searchresultswillbedisplayedinalistview. 22
RankingSystem Rankby influence(formulasagreedbyclient) • INFLUENCE (Contributors) • (Weight 1 * Number of Project Contributed) + (Weight 2 * Promotions) • INFLUENCE (Projects) • (Weight 1 * Project Success) + (Weight 2 * Promotions) • PROMOTIONS = (weight 1 * Facebook Likes) + (weight 2 * Twitter Shares) + (Weight 3 * Number of Comments) • PROJECTSUCCESS=RaisedCapital/ExpectedCapital • CAPITAL=(weight1 * Integer value of Funds) + (weight2 * Supply Items) + (weight3* Volunteer hours) 24
Demo 25
Requirements GauravDoon
System Architecture RonghuiZhang
Outlines • Overall Architecture • System Context Diagram • Process Diagram • Hardware Component Diagram • Software Component Diagram • Deployment Diagram • Detailed Architecture • Artifacts & Information Diagram • Interface Classes • Process Realization • COTS/ReuseSelections
Lifecycle planning KanQi
Development phase - Construction Iteration Duration: 2/10/14 – 4/17/14 Concept: In this phase, the development team should keeps detailing project plan and recording project progress and emphasize on implementing the system and performing testes. Deliverable: Transition Readiness Review Package, Draft Transition Readiness Review Package Milestone: Transition Readiness Review, Core Capability Drivethrough Strategy: Development and testing Development phase - Transition Iteration Duration: 4/18/14 – 5/05/14 Concept: In this stage, the development team should perform system transition by providing maintenance information, tutorial session, technical support, as well as user menu which covers different user roles. Deliverable: Operational Commitment Review Package, Transition manual, Source code Milestone: Operation Commitment Review Strategy: Deployment, Training, and Transition
Major Activities in RDCR, Development Phase-Construction Iteration 48
Major Activities in Development Phase-Transition Iteration 49