Muon g-2 Experiment at Fermilab Recycler Extraction Kicker Dan Wolff/Chris Jensen 8/29/08
SpecificationsExisting Recycler Kicker • KICK ANGLE: 1.288 mrad • FIELD RISE TIME: 1.44E-07 sec • INTEGRATED FIELD STRENGTH: 3.82E-02 (W/m^2) • HEIGHT OF MAGNET GAP: 0.052 m • WIDTH OF MAGNET GAP: 0.107 m
Using Existing Recycler Systems • Number of magnets/pulsers needed: 2 • 2 needed because of rep rate • Magnet Voltage: 14 kv • Magnet Current: 550 amps • Maximum Field: 130 gauss • Field Rise Time: 185 nsec • Tunnel Space Needed: 3.6 m
Changes/Upgrades Needed • Estimate 250 W in termination resistors • need new termination resistors, external cooling system (Flourinert cooling skid), plumbing to tunnel, and reworking magnet. • Need new (faster) charging power supplies • Shorter PFL • Need new pulser controls • Space in a nearby Service Building?????