An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TIGER GRANTInformational MeetingMarch 30, 2010 MARCH 30, 2010 1

  2. TIGER GRANT AGENDA Introduction Paddy Trusler – Lake County Commissioner Schedule of Events Bill Barron – Lake County Commissioner Skyline Project Todd Crossett - Polson City Manager MARCH 30, 2010 2

  3. TIGER GRANT INTRODUCTION – Paddy Trusler North Portion-Lake County-Map MARCH 30, 2010 3

  4. TIGER GRANT SCHEDULE OF EVENTS – Bill Barron Federal Stimulus Funds & Drop-dead Dates Contract through FHWA May 2010 Design Complete - Construction Ready for Bid September 2011 Construction Complete September 2016 MARCH 30, 2010 4

  5. TIGER GRANT COUNTY’S ESTIMATED SCHEDULE – Bill Barron Contract with FHWA April 15, 2010 Contract with Engineering Technical Consultant April 30, 2010 NEPA September 30, 2010 MARCH 30, 2010 5

  6. TIGER GRANT COUNTY’S ESTIMATED SCHEDULE – cont. Feasibility Study – Final Budget & Design/Build September 30, 2010 Design & Construction Bid Documents Complete September 1, 2011 Construction Activity Fall 2011 – June 2013 MARCH 30, 2010 6

  7. TIGER GRANT PUBLIC PROCESS – Bill Barron Tonight First Informational Meeting Additional Meetings Relative to Environmental Review & Design Project Webpage Initiated on Lake County & Polson sites www.lakecounty-mt.org www.cityofpolson.com 7 MARCH 30, 2010

  8. TIGER GRANT SKYLINE PROJECT – Todd Crossett Planned Construction 17th Avenue East to Caffrey Road Road, Retaining Wall, Guard Rail & Adjacent Pathway Estimated Construction Schedule Public Involvement & Interface Plan www.lakecounty-mt.org www.cityofpolson.com 8 MARCH 30, 2010

  9. TIGER GRANT SKYLINE PROJECT – Cont. Issues Being Addressed Access during construction Storm Water Moving utilities Tree retention Public Safety Polson Area-Map www.lakecounty-mt.org www.cityofpolson.com 9 MARCH 30, 2010

  10. TIGER GRANT WRAP UP – Paddy Trusler The Players Lake County Commission General Program Manager: Paddy Trusler Contract Management Administration, Engineering, Design, Construction Public Liaison: Bill Barron www.lakecounty-mt.org www.cityofpolson.com 10 MARCH 30, 2010

  11. TIGER GRANT WRAP UP – Cont. The Players Contract Administration Lake County Community Development: Billie Lee Project Engineer: To be determined/selected Skyline Drive Project Manager City of Polson: Ron Melvin www.lakecounty-mt.org www.cityofpolson.com 11 MARCH 30, 2010