Bridge 496 Replacement Project Scoping Meeting

Bridge 496 Replacement Project Scoping Meeting. RC1631 / Survey No. 4356 / UPI No. 11-0002-1. Location. MP 9.0 Index Galena Road @ Howard Creek . Existing Bridge. Looking Northerly at Bridge 496 . Looking downstream at Bridge 496. Issues. Structurally Deficient Bridge

telma
Download Presentation

Bridge 496 Replacement Project Scoping Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bridge 496 Replacement Project Scoping Meeting RC1631 / Survey No. 4356 / UPI No. 11-0002-1

  2. Location • MP 9.0 Index Galena Road @ Howard Creek.

  3. Existing Bridge Looking Northerly at Bridge 496 Looking downstream at Bridge 496

  4. Issues • Structurally Deficient Bridge • SSD rating 6.0 out of 100 • Load limited at 5 tons • Accessible from Jack’s Pass only, due to I-G washout at MP 6.4-6.9. • Precludes delivery of ready mix concrete. • Potential issue with 80 ft girder delivery.

  5. Issues • Residents between washout and Bridge near MP 7

  6. Issues • Existing Stopping Sight Distance does not meet EDDS for posted speed limit 35 mph. • Bridge is located on a crest curve, vs. sag. • Existing SSD is OK for 30 mph 200’ min.

  7. Issues • Drainage concept • Low added new impervious. • Mimic existing flow patterns.

  8. Issues • Thalweg clearance from existing structure appears low, at about 5 ft. • 3 ft clearance from 100 yr flood per EDDS may not be feasible, depending on hydraulic conditions, and structure type. • SWM to assist with 100 yr WSE

  9. Funding • FHWA / WSDOT • Highway Bridge Program • 2010 call for projects • FHWA grant # BROS – V 310 (002) • 80 ft bridge length • 28 ft curb to curb • Agreement # LA 7374 • PE Funds obligated 04-07-2011

  10. Budget • PE Funds: • $339,542 Federal funds (80%) • $84,885 County funds (20%) • Total PE budget $424,427 • Total estimated project cost $2,373,494

  11. Current TIP

  12. Milestones • NEPA kickoff 03/2013 • Environmental Docs approved 02/2015 • ROW complete 01/2016 • Advertisement 02/2016 • Contract Award 03/2016 • Tied bid with Index-Galena project • Open to traffic 04/2017

  13. Project Needs • Permit assistance / biological assessment • ROW / Construction easements • Geotech recommendations • Substructure type • Hydraulic • Scour • 100 yr WSE • Rip rap size

  14. Resource budgets • Provide by 04/19 • Other questions?