REVIEW ON MGNREGS IMPLEMENTATION JUNE, 2010. DISTRICT ‘MGNREGS’ CELL PURBA MEDINIPUR. ISSUES FOR DISCUSSION. Establishment of Programme Management Unit & dedicated working space & facilities(G.O. No. 6253 dated 16/09/2009).
E N D
REVIEW ON MGNREGS IMPLEMENTATION JUNE, 2010 DISTRICT ‘MGNREGS’ CELL PURBA MEDINIPUR
ISSUES FOR DISCUSSION • Establishment of Programme Management Unit & dedicated working space & facilities(G.O. No. 6253 dated 16/09/2009). • Availability of GP-wise vetted estimates to combat any event of unemployment allowance during monsoon. • Ensure maintenance of Scheme Register/Asset Register • Arrangement for timely measurement – engage GRS as per G.O. No. 2746 dated 23/04/2010
ISSUES FOR DISCUSSION • Preparation of labour budget by November 2010 & audit reply for 2008-2009 • Schemes identified for execution during monsoon season (Social forestry/nursery/plantation/river bank protection etc.) • Identification of habitation to be connected with all weather roads
Audit of MGNREGS Fund • Para wise reply from GP/PS(PIA) against the audit report for 2008-09 not received only from Sutahata and Patashpur-I Block.
Conduct of Social Audit • Complete conduct of social audit immediately, if not done within 30/06/2010. Upload findings of social audit in MGNREGA website within 15/07/2010. Only Nandakumar and Ramnagar-I uploaded one report each.
POINTS TO REMEMBER • Inspection for all schemes taken up from 2010-11 plan • Improve quality of asset creation • Maintenance of books of accounts • Disposal of complaints • Estimates become as high as 2.5 times from the approved plan, example - Moyna • Requisition forms are not filled in properly • Too many schemes implemented by GP at a particular period of time-compromising in quality
Blockwise creation of Woman Persondays as a percentage of total persondays as on 07.07.2010
Blockwise creation of SC persondays as a percentage of total persondays as on 07.07.2010
Blockwise creation of ST persondays as a percentage of total persondays as on 07.07.2010
GP WISE PERSONDAYS GENERATED(as on 07.07.2010)(BLOCK: TAMLUK) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-3799.67
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: SAHID MATANGINI) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4902.5
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: PANSKURA - I) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-2867.29
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: NANDAKUMAR) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-1382.00
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: MOYNA) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4257.55
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: KOLAGHAT) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.- 4482.69
GP WISE PERSONDAYS GENERATED(as on 07.07.2010) (BLOCK: CHANDIPUR) District Avg.- 3747.34Sub-Division Avg.-3714.08 , Block Avg.-4306.90
Blockwise Expenditure on Water conservation and water harvesting (digging of new tanks/ponds percolation tanks, small check dams etc to be indicated separately) (Sector-2) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Drought proofing (afforestation and tree plantation and other activities to be indicated separately)(Sector-3) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Micro irrigation works (minor irrigation canals and other activities to be indicated separately) (Sector-5) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Provision of irrigation facility,horticulture & plantation to land owned by : (scheduled castes and scheduled tribes, beneficiaries of land reforms and beneficiaries of IndraAwasYojana ) (Sector-8) as per percentage of total expenditure upto JUNE , 2010
Blockwise Expenditure on Renovation of traditional water bodies (desalting of tanks/ ponds, desolating of old canals, desolating of traditional open well etc. to be indicated separately) (Sector-7) as per percentage of total expenditure upto JUNE, , 2010
Blockwise Expenditure on Land development(plantation, land leveling other activities to be indicated separately)(Sector-6) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Flood control and protection (drainage in water logged areas, construction and repair of embankment to be indicated separately) (Sector-4) as per percentage of total expenditure upto JUNE, 2010
Blockwise Expenditure on Rural connectivity(Sector-1) as per percentage of total expenditure upto JUNE, 2010