1 / 30

Renovation of Niagara Springs Steelhead Hatchery

This project aims to renovate the Niagara Springs Steelhead Hatchery to provide a larger indoor nursery environment for steelhead eggs and fry. The goals include eliminating fish pathogens from the water, repairing deteriorating concrete raceways, and expanding administrative workspace.

temme
Download Presentation

Renovation of Niagara Springs Steelhead Hatchery

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Renovation of Niagara SpringsSteelhead Hatchery LSRCP Hatchery Production Meeting March 13, 2013

  2. Project Goals • Create a larger indoor nursery environment for steelhead eggs and fry with natural photoperiod • Eliminate fish pathogens from influent spring water • Remove debris from influent and effluent spring water • Repair deteriorating concrete raceways • Replace bird control netting • Expand administrative workspace, shop and storage buildings

  3. Phase 1 Construction 2012

  4. Phase 2 Construction 2013

  5. Site Design Priorities: • Retain gravity flow water source • Provide pathogen free water for incubation and indoor rearing • Install a vat size and quantity that allows an even distribution of fish when moved into outdoor raceways • Provide ability to rear fish indoors until they were large enough for marking Challenges with space for hatchery building: • Building requires a large footprint with little land available • Back wall of hatchery building supports the entrance road • Need to maintain access between raceways and hatchery building for fish tankers • Creating a vat room layout that included enough space for the vats while maintaining a clear separation of the two different stocks

  6. Existing Indoor Rearing: Total number of vats = 21 Vat dimensions: 8’L x 2.5’W x 2.5’D Rearing volume per vat: 37.5 ft3 Max flow for incubation = ~ 3 cfs Max flow per vat = 47.6 gpm Max density index = 0.88 lbs/cf/in Max flow index = 0.70 lbs/gpm/in Approx. eggs/fry per vat = ~ 50,000 Split inventory – eggs & fry Size at transfer to outdoor raceways = 1,000 fpp

  7. Indoor Rearing Design Criteria: • Total number of vats = 38 (16 OFH, 22 PFH) • Vat dimensions: 50’L x 4’W x 3.5’D • Rearing volume per vat : 552 ft3 • Max flow for incubation = 18 cfs • Max flow per vat = 212 gpm • Max density index = 0.35 lbs/cf/in • Max flow index = 0.85 lbs/gpm/in • Approx. eggs/fry per vat = ~ 55,000 • Entire inventory received as eyed eggs • Target size at transfer to outdoor raceways = 90 fpp (at marking)

  8. Intake & Filter Building: • Water source → Niagara Springs middle pool via RVTC canal • Maintain gravity flow • No in-stream work (BRS) • Flow meters per IDWR requirements • Two sets of drum and disc filters for different size debris • 2 drum filters – 100 µm • 2 disk filters – 30 µm • Full 18 cfs can be passed through either set of filters without affecting operation • Filters and backwash spray system operated on timer or head differential

  9. UV System: • Pathogens of concern: • Infectious Hematopoietic Necrosis (IHN) • Infectious Pancreatic Necrosis (IPN) • Furunculosis • Enteric Red Mouth (ERM) • Viral hemorrhagic septicemia (VHS) • Whirling Disease (WD) • Cold Water Disease (CWD) • Nucleospora salmonis • UV doses for inactivation of these pathogens → 5,000-150,000 mJ/cm2 • All but IPN inactivated at 40,000 mJ/cm2 or below • IPN requires system that is 3-4 times larger

  10. UV System (continued)… • Design dose = 60,000 mJ/cm2 (minimum dose at end of lamp life) • Total of three UV vessels • 2 for operation, 1 backup • UV system alarming: • Lamp failure • Low dose • Generator backup for filter building and UV system

  11. Alarming/SCADA

  12. Vat Room • Size of vat room: • Old vat room = 1,340 ft2 • New vat room = 18,500 ft2 • Number of rearing vats: • Old vat room = 21 vats • New Vat room = 38 vats • Total rearing volume: • Old vats = 750 ft3 • New vats = 21,000 ft3 • Natural lighting

  13. Additional Rooms • Feed Room • Storage of palletized feed • Workbench for weighing feed • Egg Room • Receive, enumerate and disinfect eyed eggs • Laboratory use • Boot Room • Vat room gear storage • Mud Room • Remove outdoor gear • Water fountain • Restroom • Visitor Room • View of vat room • Display tank • Information, brochures, etc. • Water fountain • Restroom

  14. Administrative Area • Office • Manager’s office • 3 Workstations • Seasonal room • Conference Room • Break/lunch room • School tours • Meetings

  15. Phase 2 • Raceway water intake modifications • Outdoor raceway modifications • Bulk feed storage modifications • Bird netting modifications • Install discharge traveling screens • Construct shop building • Construct storage building

  16. Raceway Water Intake • Leaf debris during the spring and fall plugs head screens and tail screens on raceways • Can be unpredictable - frequent monitoring by staff during peak loads and stormy weather • Install stainless steel inclined traveling screens to remove most debris • Operate on automated schedule or head differential • Traveling screen openings the same as raceway screens

  17. Raceway Modifications • Total of 19 raceways • 14 original from 1966, 5 additional in 1993-1994 modification • Repair or replace raceway walls (original 14 raceways) • Concrete cracking and spalling • Rusting and deterioration of keyways • Replace steel keyways in original 14 raceways with stainless steel keyways to address corrosion • Install additional keyways in all 19 raceways • Keyways currently at 100 foot intervals • Install additional stainless steel keyways at 50 foot intervals

  18. Traveling Bridge Replacement • Split large traveling bridge into 2 smaller bridges • Reduce maintenance on bridges • Eliminate racking, derailing • Switch to more reliable direct drive power system • Allow for bird netting supports on raceway wall • Replace all feeders

  19. Bulk Feed Storage • Raise height of bulk feed storage hoppers to allow personnel to perform maintenance more easily • Raise height of feed conveyor system to eliminate the risk of head injuries Bird Netting • Install support system on raceway wall to reduce sag • Replace existing 2-3” mesh bird netting with ¾” mesh netting

  20. Discharge Traveling Screens • Issues with large mats of algae breaking loose and leaving ponds • NPDES concerns • Plugging RVTC screen • Two discharge points: Niagara Springs Creek and RVTC canal • Install stainless steel inclined traveling screens to remove debris • Similar design and operation to system at raceway intake

  21. Shop Building • Mechanical room • Lab room • NPDES sampling equipment • Pathology • Storage bay with mezzanine • Vehicle Bay • Bigger shop area • 640 ft2 vs. 880 ft2 • Gear room • Store gear used in raceways • Restroom • Drinking fountain

  22. Storage Building • Lawn equipment storage • Large center bay for 10-ft raceway screen storage • Other miscellaneous storage • Covered, fenced outdoor storage area • Bulk fuel storage

  23. Project Summary Address Operational Constraints • Enlarge incubation and early rearing for improved fish health • Reduce maintenance and repair costs • Improve predator control • Enlarge office workspace Incorporate Modern Fish Culture Technology • Water filtration and UV disinfection • Improve bio-security • State-of-the art alarming and standby power • Debris removal screening

  24. Questions?

More Related