Nevada • 2.8 million people (2 million in Clark Co.; 430,000 in Washoe Co.) • 5,380 NDOT-maintained centerline miles (654 Urban; 4,726 Rural) • 17 counties • 4 MPOs
Nevada Constitutionally protected State Highway Fund • Driver’s license & registration fees • Fuel tax • 18.455¢ per gallon (27.75¢ for diesel) • 6.35¢ county mandatory tax • Up to 9¢ county optional tax • Washoe County indexing since 2003 State Highway Fund revenue: about $1 Billion
Nevada DOT • Board oversight (Governor, Lt. Gov., Controller, 4 Appointees) • 1,800 employees (200 admin.; 400 pre-const.; 400 const.; 800 maintenance) • Three “Districts” • 259 fatalities (2012)
NDOT Research • RDT annual apportionment: $1.7 million • UTC participation: $250,000 • Good department support • Excellent support from administration!!
Project Selection Process(Through Federal Fiscal 2014) • Followed our 2003 Research Manual • An annual process • Relied on two interdisciplinary groups of professionals within the Department: • The Research Advisory Committee • The Research Management Committee
Oct 16 – Dec 31: Conduct Meetings/Brainstorm Sessions to Identify Research Needs Jan 1 - 31: Develop/Prepare Problem Statements December January November February Feb 1 – 28: Sort, Screen and Clarify New Problem Statements Oct 1-15: Solicitation Begins; Distribute Problem Statement Form October March Mar 1 – 15: RAC Evaluates and Prioritizes Problem Statements September April Sep 1-30: Agreement Drafting / Develop SPR Work Program Mar 16 -June 15: Proposal Development/Submission May August June Aug 1 – 31: RMC Meets to Approve New Research Priorities Jun 15 – July 31: RAC Meets to Evaluate and Prioritize New Proposals July Research Project Selection Process(Through Federal Fiscal 2014) Research Timetable
Project Selection Process(Beginning Federal Fiscal 2015) • Quarterly • Problem Statements • Proposals • Eight Expert Task Groups • SPR Task: Strategic Research Plan • Update our Research Manual
Thank You! Ken Chambers Research Chief Nevada DOT 1263 South Stewart St. Carson City, NV 89712 (775) 888-7220 kchambers@dot.state.nv.us