Lina c4 connection Work to be done and draft planning. JBL-12/09/2013. 2 different areas. LBE line upgrade Linac2/Linac4 interface. Linac4/Linac2 interface What to be done ?. Shielding wall Emergency exit Château Chicane. Linac4/Linac2 interface. LBE upgrade. Draft Planning.
E N D
Linac4 connectionWork to be done and draft planning JBL-12/09/2013 JBL - 12/09/2013
2 different areas. • LBE line upgrade • Linac2/Linac4 interface JBL - 12/09/2013
Linac4/Linac2 interfaceWhat to bedone? • Shieldingwall • Emergency exit • Château • Chicane JBL - 12/09/2013
Linac4/Linac2 interface JBL - 12/09/2013
LBE upgrade JBL - 12/09/2013
Draft Planning • 4 weeks for hardware and beam commissioning (very conservative considering the TL will have been already commissioned up to the debuncher (H- stripping test stand). • Time needed for the L2/L4 : 7 weeks • Time needed for LBE : 4 weeks (cool down not taken into account!). • Beam could be delivered to PSB 11 weeks after the Linac2 shut down. • Work in the LBE area cannot be done if ions in the PS. • If an ion run right after Linac2 shutdown, no cool down time necessary for the LBE work. JBL - 12/09/2013