1 / 30

The Future of Section 74

The Future of Section 74. Peter Goode Nottingham City Council. Apology. Section 74. Why Section 74? 2001 Scheme Interpretation and Challenge Review of the Scheme New Emphasis Revised Scheme. Section 74. Providing incentives to: Complete works without delay Minimise disruption

terra
Download Presentation

The Future of Section 74

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Future of Section 74 Peter Goode Nottingham City Council

  2. Apology

  3. Section 74 • Why Section 74? • 2001 Scheme • Interpretation and Challenge • Review of the Scheme • New Emphasis • Revised Scheme

  4. Section 74 • Providing incentives to: • Complete works without delay • Minimise disruption • Maximise productivity • Meet public expectation

  5. Trying to avoid this …

  6. .. caused by this ..

  7. .. and this.

  8. ICE Report • “…. road works by utility companies are the principle cause for AVOIDABLE delay.” • Total cost per day of delayed traffic flow is £3160 per excavation – based on • 500 vehicles each way per day • 15 minutes delay • Average earnings £20,000 = £0.20 / min

  9. The cost of delay …

  10. .. caused by this.

  11. The cost of delay • Peak period flow assumed 1veh / sec • Peak period assumed for 1 hour • Peak period vehicles = 3600 • Cost of delay = £0.20 x 3600 = £720 / min • If typical delay is half hour, cost = £21,600

  12. Avoidable delay • Whatever the reason avoidable delay must be addressed as a matter of priority

  13. Section 74 Schemes • Allow charges for occupation when unreasonably prolonged • Promote proactive management of works • Encourage planning, estimating and control of works to avoid charges • Allow updating and revised plans to complete within time and avoid charges

  14. 2001 Scheme • Emphasis on longer duration works – 5 day prescribed period • Ministers decided 3 day prescribed period • Weekends available at no charge • Reinstatement category is proxy to traffic flow • Remedial works have independent duration

  15. 2001 Scheme • Simple scheme • 2 x 2 matrix of charges • Charges proportional to works • Used existing notice systems • Avoided need for additional inspections • Minimised cost of operation

  16. Interpretation and Challenge • Regulations contained error(s) • Regulations are ‘gibberish’ written by a ‘demented computer’ • Use of notices are undermined by the right to rebut • Remedial works included in original period

  17. Scheme Review • Identify successes and failures • Identify loopholes • Catch me if you can v Income stream • Charge Evasion v Charge Avoidance • Keep Notices Live v Complete Works

  18. Review Issues • Scheme undermined by regulation errors • Ambiguities in noticing requirements • Interpretation by developers and users • Lack of early intervention • Too much time spent collecting charges

  19. Emphasis of New Scheme • Ease of operation • Synergy with permits and TMA generally • DfT remit • Narrowed scope • Higher charges • Inspection of works

  20. Narrowed Scope • Emphasis towards higher vehicular flows • Exempt lower category streets • Different views held – Compromise for consultation • Occupation v Congestion • Variance from TMA • Vehicle congestion v Pedestrian disruption • Which streets included? • Which works included?

  21. Charges (Per Day)

  22. Inspection of Works • Notice submission dates do not apply – inspections required • 10% inspection allowance for S74 to be implemented by Inspections group • Monitor progress • Check incursion • Check site clearance

  23. New Features • 2 day prescribed period • Incursive works only • Exempt non-traffic sensitive Cat 3 and 4 • Exempt pedestrian streets • Parallel use of FPN powers

  24. Invoicing • More stringent process • Defined time periods for action by each party • Minimises prolonged dispute • Encourages early settlement • Improves budget control

  25. Summary • New scheme to take account of • Experience • Legal judgement • Traffic Management Act • Not all issues agreed • Consultation to influence final scheme • Application across work by all parties

  26. Works Clear or Signs left on site?

More Related