Woodrow Wilson Bridge Reconstruction Test Embankments for Route 1 Interchange. June 4, 2001. VDOT. WWB TEST EMBANKMENTS. Recommended by FHWA Limited Scope/Budget ($2 Million) Limited Time for Completion (1/00 to 2/01). VDOT. OBJECTIVES FOR TEST EMBANKMENTS. Assess Rates of Consolidation
E N D
Woodrow Wilson Bridge ReconstructionTest Embankments for Route 1 Interchange June 4, 2001 VDOT
WWB TEST EMBANKMENTS • Recommended by FHWA • Limited Scope/Budget ($2 Million) • Limited Time for Completion (1/00 to 2/01) VDOT
OBJECTIVES FOR TEST EMBANKMENTS • Assess Rates of Consolidation • Verify Predicted Settlements • Optimize PV Drain Spacings • Determine Mix Design Parameters • Verify Design Assumptions • Verify Constructability • Refine/Develop Specifications VDOT
P.V. DRAIN (PVD)TEST EMBANKMENT • 8’ of Granular Fill over 10’-12’ of Soft Alluvial/ Organic Clays (A1) over Terrace Sand/Gravel • 90’ x 45’ Embankment With Vertical MSE Face • Embankment 14’ +/- Above Original Ground • 6’ of Surcharge; 2’ Drainage (Sand) Blanket • 9,000 Tons of Select Material VDOT
PVD INSTRUMENTATION • 12 Settlement Plates • 3 Observation Wells • 4 Vibrating Wire Piezometers • 3 Inclinometers • 2 Magnetic Extensometers • 16 Settlement Pins; 8 PK Nails VDOT
PVD INSTRUMENTATION • Clustered for Constructability • Time for Installation included in Contract Specifications • Installation/Monitoring by VDOT (Owner) • Penalties (Time/Money) Assessed for Contractor Damage to Instruments VDOT
DESIGN INFLUENCE OF PVD TEST EMBANKMENT • 5’ Spacing instead of 4’ Spacing • 6-Month Consolidation Stages • Estimated Direct Savings of $650,000 • Contractual “Lessons Learnt” (Pre-drilling; Pay quantities; Production Rates; Constructability) VDOT
DEEP MIX METHODS (DMM)TEST EMBANKMENT • “Wet” and “Dry” Mix Columns (Single Augers) • “Wet” Mix Panels (Triple Augers) • 8’ of Granular Fill over 32’ of Very Soft Organic/Alluvial Clays (A1) over Terrace Sand/Gravel • Organic Contents 1%-15% VDOT
DMM INSTRUMENTATION • 8 Settlement Plates • 1 Observation Well; 2 Piezometers • 4 Vibrating Wire Piezometers • 7 Inclinometers (6 Vert.; 1 Horiz.) • 2 Magnetic Extensometers • 8 Pressure Cells • 11 Settlement Pins • 6 Thermistors VDOT
DESIGN INFLUENCE OF DMM TEST EMBANKMENT • Specified “Wet” Mix Exclusively • 2’ Construction Platform (Sand) • Contractual “Lessons Learnt” (Acceptance Criteria; Mix Design Criteria; Production Rates; Constructability) VDOT