170 likes | 540 Views
NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011. Click to proceed……. Dear Sir,
E N D
NEW TOWN HEIGHTS DLF – KAKKANADWORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..
Dear Sir, We are glad to inform you that the construction activities are in full swing at New Town Heights DLF – Kakkanad, in all the launched towers. Please find below the Tower wise progress report. • Tower 6 / Block N • 17th floor slab shuttering work in Progress. • Block work progressing on the 10th floor. • Ceiling plastering progressing on the 5th floor. • Tower 6 / Block P • 17th to 18th floor slab column raising in progress. • Block work in progress on the 11th floor. • Ceiling plastering progressing on the 3rd floor • Tower 6 / Block Q • 18th floor slab casting in progress. • Block work in progress on the 11th floor. • Ceiling plastering progressing on the 5th floor. • Tower 5 / Block K • 16th floor slab shuttering in progress. • Block work in progress on the 6th floor. • Ceiling plastering progressing on the 9th floor. • Tower 5 / Block L • 15th floor slab casting in progress. • Block work in progress on the 7th floor. • Ceiling plastering in progress on the 9th floor. • Tower 5 / Block M • 15th floor slab shuttering in progress. • Block work in progress on the 7th floor. • Ceiling plastering progressing on the 8th floor.
Tower 4 / Block H • Ground to 1st floor column raising in progress. • Tower 4 / Block J • 2nd floor slab shuttering work in progress. • Tower 3 / Block G • 16th floor slab shuttering work in progress. • Block work progressing on the 3rd floor. • Ceiling Plastering in progress on the 3rd floor. • Tower 2a / Block D • 9th to 10th floor column raising in progress. • Block work in progress on the 3rd floor. • Ceiling plastering work in progress on the ground floor. • Tower 2b / Block E • 6th to 7th floor column raising in progress. • Block work in progress on the ground floor. • Ceiling plastering in progress on the 2nd level podium floor. • Tower 2b / Block F • 7th floor slab shuttering in progress. • Block work in progress on the 2nd floor. • Ceiling plastering in progress on the 1st floor.
Tower 1 / Block A • 16th floor slab casting completed. • Block work progressing on the 8th floor. • Ceiling Plastering in progress on the 7th floor. • Tower 1 / Block B • 18th floor slab casting completed. • Block work progressing on the 10th floor. • Ceiling plastering work in progress on the 8th floor. • Tower 1 / Block C • 12th to 13th floor column raising in progress. • Block work progressing on the 5th floor. We are also attaching the site progress photographs along with this.
Block –N 17th Floor Slab Shuttering in Progress Block –P 17th to 18th floor Column Raising in Progress Block –Q 18th Floor Slab Reinforcement work in Progress TOWER 6 Block work 10th floor in Progress. Ceiling Plastering 5th Floor in Progress. Block work 11th floor in Progress. Ceiling Plastering 3rd floor in Progress Block work 11th floor in Progress. Ceiling Plastering 5th floor in Progress
Tower 5 Block –M 15th Floor Slab Shuttering work in Progress Block –K, 16th floor slab Shuttering & Reinforcement work in Progress Block –L, 15th Floor slab reinforcement work is in Progress Block work 7th floor in Progress. Ceiling Plastering 8th floor in Progress Block work 6th floor in Progress. Ceiling Plastering 9th floor in Progress Block work 7th floor in Progress. Ceiling Plastering 9th floor in Progress
TOWER -4 (Block H) Block –H Ground floor to 4th floor Column Raising in Progress
TOWER 4-(Block J) Block –J 2nd floor Slab Shuttering work in Progress
TOWER-3 (Block G) Block G 16th floor slab shuttering work in Progress Block work 3rd floor is in Progress & Ceiling Plastering 3rd Floor in Progress
Tower -2a(Block D) Block –D 9th to 10th floor Column Raising in Progress Block work 3rd floor is in Progress & Ceiling Plastering Ground Floor in Progress
Tower -2b(Block E) Block –E 6th to 7th floor Column Raising in Progress. Block work Ground floor is in Progress & Ceiling Plastering 2nd level podium Floor in Progress
Tower -2b(Block F) Block –F 7th Floor Slab Shuttering work in Progress Block work 2nd floor is in Progress & Ceiling Plastering 1st Floor in Progress
TOWER 1 Block –A 16th floor slab casting completed Block –C 12th to 13th Floor column raising in progress Block –B 18th Floor Slab casting completed. Block work 8th floor in Progress. Ceiling Plastering 7th Floor In Progress Block work 5th Floor in Progress Block work 10th floor in Progress. Ceiling Plastering 8th Floor In Progress
Block –Q 1st level podium Slab Completed Block –E & F Podium Pile cap work completed & column raising is in Progress
MARKETING OFFICE -MODEL FLAT Signature Tower Model Flat Partition Wall & False Ceiling Work in Progress Tower 2 Model Flat Partition Wall & False ceiling Work in Progress