An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Site selection and setting out Biogas ToT Course May 10 – 15, Kampala, Uganda

  2. Site selection Main considerations • Easy construction works • Water logging • Rock • Minimum construction cost • Easy operation and maintenance • Feeding • Use of main gas valve • Composing and use of slurry • Checking of gas leakage • Draining condensed water from pipeline. • The site should guarantee plant safety

  3. Site requirements I • Constant, high ambient temperature • Even and smooth surface • Slightly in elevated than the surrounding • Close to: • dung collection point • water point • gas application point • 2 meter away from foundations • Space for plant and compost-pit • Away from wells to avoid ground water pollution

  4. Site requirements II • Sufficient distance to trees • Adequate distance from main trail or unsafe areas • Good bearing capacity of soil • Limited space: cattle shed on top of the plant after proper backfill • Reasonably far from any machine producing vibration on soil

  5. Setting out

  6. Setting out

  7. Lay-out example Toilet Slurry Pit Inlet Digester Outlet Slurry Pit

  8. 30 – 50cm above ground level Reference line > 20 cm 30 cm Reference line

  9. Thank you