2009 SERTP Economic Studies
2009 SERTP Economic Planning Studies
2009 SERTP Five Economic Planning Studies • North Georgia to FRCC • 650 MW • SCE&G to Georgia • 1000 MW • Gulfport, MS to Georgia • 1000 MW • Washington County, GA to Georgia • 5000 MW • Savannah, GA to Southern Balancing Authority • 400 MW Summer Peak • 1000 MW Off Peak
2009 SERTP Power Flow Cases Utilized • Study year: 2014 • Load Flow Cases: • 2009 Series Version 2A • Summer Peak with 2250 MW Interchange to FRCC, 3600 MW to FRCC, and Shoulder
2009 SERTP Five Economic Planning Studies • Final Report Components: • Thermal Analysis • DC contingency analysis to attain monitored/contingency pairs with Siemens PSS MUST • AC verified with Siemens PTI PSS/E • Interface Transfer Capability Impacts • Stability Impacts • Potential Solutions • Transmission Projects and Cost Estimates
2009 SERTP • The following information does not represent a commitment to proceed with the recommended enhancements nor implies that the recommended enhancements could be implemented by the study date of 2014. • These potential solutions only address constraints identified within the Southern Balancing Area that are associated with the proposed transfers. Other Balancing Areas were not monitored which could result in additional limitations and required system enhancements.
North Georgia to FRCC 650 MW
Source Sink North Georgia to FRCC: 650 MW • Transfer Type: Generation to Load • Source: 500 kV, Murray County, GA • Sink: 650 MW of FRCC load scaled up • 488 MW Florida Power & Light • 162 MW Progress Energy Florida
650 MW North Georgia to FRCC: 650 MW • Transfer Type: Generation to Load • Source: 500 kV, Murray County, GA • Sink: 650 MW of FRCC load scaled up • 488 MW Florida Power & Light • 162 MW Progress Energy Florida
North Georgia to FRCC: 650 MW Transmission System Impacts • Thermal Constraints Identified: • One (1) 500kV Line • One (1) 230 kV Line • Six (6) 115 kV Lines • Interface Constraints Identified: • One (1) 500 / 230 kV Transformer • One (1) 230 kV Line • Stability Constraints Identified: • None Identified
North Georgia to FRCC: 650 MW Transmission Project Estimates 1 Limiting element is within FRCC Total Cost: $53,100,000
Potential Enhancements P2 P1 P6 P5 P7
SCE&G to Georgia 1000 MW
Source Sink SCE&G to Georgia: 1000 MW • Transfer Type: Load to Generation • Source: SCE&G Load • Sink: Georgia Generation
SCE&G to Georgia: 1000 MW Transmission System Impacts • Thermal Constraints Identified: • One (1) 230 / 115 kV Transformer • One (1) 115 kV Line • Interface Constraints Identified: • One (1) 500 / 230 kV Transformer • Two (2) 230 kV Lines • One (1) 230 / 115 kV Transformer • Four (4) 115 kV Lines • Stability Constraints Identified: • None Identified
CENTER Thermal Constraints
SCE&G to Georgia: 1000 MW Transmission Project Estimates Total Cost: $48,300,000
SCE&G to Georgia: 1000 MW Transmission Project Estimates 1Project I1 alleviates the need for Project P1 Total Cost: $44,500,000
CENTER Potential Enhancements P2 P1
P1 Potential Enhancements P2 I2 I1
Gulfport, MS to Georgia 1000 MW
Source Sink Gulfport, MS to Georgia: 1000 MW • Transfer Type: Generation to Generation • Source: 500 kV, Harrison County, MS • Sink: Georgia Generation
1000 MW Gulfport, MS to Georgia:1000 MW • Transfer Type: Generation to Generation • Source: 500 kV, Harrison County, MS • Sink: Georgia Generation
Gulfport, MS to Georgia:1000 MW Transmission System Impacts • Thermal Constraints Identified1: • Six (6) 230 kV Lines • Nine (9) 115 kV Lines • Interface Constraints Identified2: • Two (2) 230 kV Lines 1 Constraints remaining after implementing stability enhancement 2 Constraints remaining after implementing all thermal enhancements
Gulfport, MS to Georgia:1000 MW Transmission System Impacts Continued • Stability Constraints Identified: • With the additional transfer of 1000 MW from Gulfport, MS to the Georgia ITS, a fault on the Daniel – McKnight 500 kV transmission line could result in all of the units within the local area to pull out of synchronism with the rest of the Eastern Interconnect.
Gulfport, MS to Georgia:1000 MW Transmission Project Estimates
Gulfport, MS to Georgia:1000 MW Transmission Project Estimates Total Cost: $457,010,000
Potential Enhancements P9 P8 P10 P4 P5 P1 P2 P12 P3 P6 I1 P11
Washington County to Georgia 5000 MW
Source Sink Washington Co. to Georgia:5000 MW • Transfer Type: Generation to Generation • Source: Washington County, GA • Sink: Georgia Generation
5000 MW Washington Co. to Georgia:5000 MW • Transfer Type: Generation to Generation • Source: Washington County, GA • Sink: Georgia Generation
Washington Co. to Georgia:5000 MW Transmission System Impacts • Thermal Constraints Identified: • Ten (10) 500 kV Lines • Four (4) 500 / 230 kV Transformers • Thirty (30) 230 kV Lines • Six (6) 230kV / 115 kV Transformers • Twenty-three (23) 115 kV Lines • Interface Constraints Identified: • Three (3) 230 kV Lines • Stability Constraints Identified: • None Identified