Working with State and Federal Regulatory and Land Management Agencies Navajo Nation Environmental Protection Agency. Navajo Generating Station (NGS) BART Process. U.S.BOR =24.3%, SRP = 21.7%, LADWP = 21.2% , APS = 14%, NPC = 11.3%, TEP = 7.5%. Unit 1, 2 and 3 = 750 MW each.
E N D
Working with State and Federal Regulatory and Land Management Agencies Navajo Nation Environmental Protection Agency
Navajo Generating Station (NGS) BART Process U.S.BOR =24.3%, SRP = 21.7%, LADWP = 21.2% , APS = 14%, NPC = 11.3%, TEP = 7.5% Unit 1, 2 and 3 = 750 MW each
Installation Period Required if SCR is required in this BART 2011 3 2 1 3 2 1 3 2 1 DOI Approvals (Comp - 7/1/18) SCR Design and installation Duration NGS Site Lease Termination (12/23/19) NEPA Process (Comp - 12/31/17) 2nd SIP/FIP update for RHR is due in 2018 Legal Challenges (2 years ?) Lease Negotiations and Approvals (12/31/11) NGS Owners Initial Proposal - GDReeves
NGS Study • Evaluate technical, economic and legal feasibility of options • DOI coordinate the study with DOE • Bureau of Reclamation contract with NREL • Stakeholder Involvement DOI, NGS Owners, CAWCD, Navajo Nation, Hopi Tribe, CAP water‐using Indian tribes, Conservation Groups and other interested NGOs