An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hemet High Phase 2 Modernization & ExpansionApril 25th, 2012: Theater –(l) Pass-thru windows have been installed. (r) Pass-thru window and casework installed at ticket booth.

  2. April 25th, 2012: Theater – (l): Sink casework at scene shop. (r): T-grid ceiling system installed at lobby.

  3. April 25th, 2012: Theater – (l): Projection screen has been hung. (r)-Fine grading and irrigation progressing towards the Theater.

  4. April 25th, 2012: Science Building - (l): Vinyl floor tile is complete at this classroom . (r)-Teachers work station.