260 likes | 286 Views
The German Approach on Safety of Natural Gas Distribution Pipelines. WORKSHOP ON THE PREVENTION OF ACCIDENTS OF GAS TRANSMISSION PIPELINES (The Hague, 8 to 9 March 2006) Klaus Söntgerath State Authority for Mining, Energy and Geology. Contents. Introduction Regulations Approval processes
E N D
The German Approach on Safety of Natural Gas Distribution Pipelines WORKSHOP ON THE PREVENTION OF ACCIDENTS OF GAS TRANSMISSION PIPELINES (The Hague, 8 to 9 March 2006) Klaus Söntgerath State Authority for Mining, Energy and Geology
Contents • Introduction • Regulations • Approval processes • Governmental Control • Technical Experts • Risk Assessment • Conclusions
Gas Pipelines in Germany • Demand of Natural Gas in 2004: 119 * 109 m³ • 380.000 km of Pipelines • Supplier Countries 2004:
Gas Pipeline Grid roundabout 240 km
Scope of the paper • Pipelines for transportation and distribution of Natural Gas • Incidental pressure above 16 bars • Pipelines that leave the area of a plant • Pipeline includes all elements for the operation of the pipeline
Legislation • General legislation • Energy Trade Act • Act for Safety of Products and Equipment • Special legislation • Gas Pipeline Ordinance • e. g. safety corridor, protection against third party activities, crossing of pipelines, corrosion protection, safety equipment, pressure measurement, permanent manned station, route inspection, recording, stand-by duty • Risk assessment is not required!!!
Technical Guidelines of DVGW • Detailed rules • State of the Art • The following of the State of the Art is assumed if the technical guidelines of the “DVGW - The German Technical and Scientific Association for Gas and Water“ are observed e. g. • G 463 Steel Gas Pipelines with an incidental pressure higher than 16 bars; Construction –Working Paper- 12/01(G 463 Gasleitungen aus Stahlrohren von mehr als 16 bar Betriebsdruck; Errichtung -Arbeitsblatt- 12/01)
Technical Guidelines of DVGW • Gas Pipeline Ordinance and G 463 • Requirements: e. g. materials, safety factors, corrosion protection • Risk assessment is not required!!! • e. g. wall thickness • Depends on pressure, material, safety factor • Constant over a whole pipeline • Depends not on risks e. g. density of population
1st Step - Land Use Planning • Land Use Planning Act • Land Use Planning of the States • Regional Land Use Planning • Land Use Planning Ordinance:gas pipelines diameter > 300 mm:Approval process for land use planning • Approval process • Including assessment of spatial impacts on the environment and public hearing • Simplified approval process • States or regional Land use plans include the pipeline – no approval process on Land Use Planning necessary • Decision on Land Use Planning by Regional Authority
2nd Step - Approval Process • Diameter > 300 mm • Art. 43 Energy Trade Act, established: 2001 • EIA needed (regulated or decision by authority) • Approval process including public hearing and EIA (Planfeststellung) • EIA not needed (regulated or decision by authority) • Formal approval process without public hearing and EIA (Plangenehmigung) • Diameter < or = 300 mm: • Art. 5 Gas Pipeline Ordinance; Notification Process, established: 1974
Demands in Approval Process • Notification Process • (Diameter < or = 300 mm, length > 1000 m) or • included in the approval processes • The construction of a Gas Pipeline • is to notify to the competent authority • at least 8 weeks before beginning of the construction • including all important documents of pipeline integrity • including a statement of a technical expert: The pipeline meets the requirements of the Gas Pipeline Ordinance
Demands in Approval Process • The competent authority can refuse the plan • If it is not proven that the construction and operation meets the requirements of the Gas Pipeline Ordinance • If further requirements according to the Gas Pipeline Ordinance are necessary • The construction of the pipeline can be started • After 8 weeks after the information of the competent authority • In case of refusal of the plan after the elimination of the fault(s)
Demands before Start of Operation • Before Start of Operation • Pre-Certification of a technical expert about • Test of tightness and stability • Existing of safety equipment • No doubts about pipeline integrity • Some time after the Pre-Certification • Final assessment of the technical expert whether the pipeline meets the requirements of the Gas Pipeline Ordinance • Final Certification
Governmental Control • Operator has to supervise an maintain his pipelines (Operator Responsibility) • The Competent Authority • can require data of the supervision • can inspect the plants • can require supervision measures • In special cases • Inspections by technical experts because of supervision data
Announcements to the Competent Authority • Setting a pipeline out of operation because of critical circumstances • Accidents that caused dangerous wounded or killed people • Leaks, dangerous for the vicinity • Incidents with major material damages • Circumstances that people or objects expose to danger
Certification of Technical Experts • Technical Expert Organisations • Listed in Gas Pipeline Ordinance • Personal certification of each Technical Expert by the States • Exchange of lists of Technical Experts between the States
Technical Experts - Tasks • Statement forNotification Process • Pre-Certification • Final Certification • Assessment of pipelines e. g. • in case of incidents • By order of competent authority • Statement before works at pipelines in operation
Risk Assessment An Example
Risk Assessment – Wind Turbines • To assess – risk of Wind Farms in the vicinity of Gas Pipelines • Assessed risks • Loss of a rotor blade • Loss of a rotor • Break of the tower • Probabilistic assessment: limit 10-6 damages per year • Result: lowest distance between wind turbine and gas pipeline
Conclusions • Germany has established an hierarchic legislative System on gas pipelines (Act – Ordinance – Rules) • Approval processes for land use planning and pipeline projects are in use • Greater projects need EIA and public hearing • Supervision of pipelines in operation consists of Operator Responsibility – Authorities Control – Statements of Technical Experts • Regulations have a deterministic approach – Risk Assessments are only used in single cases