Construction 2009 Progress Report. Indian Brook Elementary. Trailer Classrooms. Purchase and construction of trailer classrooms postponed pending budget approval meeting April 12 th Concern over wetlands regulations paperwork to be discussed at meeting Alter timeline for completion?.
E N D
Construction 2009 Progress Report Indian Brook Elementary
Trailer Classrooms • Purchase and construction of trailer classrooms postponed pending budget approval meeting April 12th • Concern over wetlands regulations paperwork to be discussed at meeting • Alter timeline for completion?
Building A Roof Repair • School Choice Revenue covers 75% of roof repair cost • Ideas for generating additional funds • Work to begin June 20th
Mathilda H. Parker Library • No delays expected • Tasks remaining: • Carpet • New shelves (to be delivered mid-May) • Re-organization of periodicals section
Mandate Review • Construct 5 trailer classrooms to accommodate upcoming enrollment increases in Grades K-6 due to closing of John Barnes Elementary • Fix Building A Roof using School Choice revenue • Complete renovations of Mathilda H. Parker Library by December 15, 2009