1 / 15

MICE Beamline: Plans for initial commissioning.

MICE Beamline: Plans for initial commissioning. Target, detectors, particle production Upstream beamline Downstream beamline: Step 1 Jan 20 - March , Step 2 April – June. Summary. Kevin Tilley, 16 th November. - 75days until commissioning. (& 9hours). Charge.

tiva
Download Presentation

MICE Beamline: Plans for initial commissioning.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Beamline: Plans for initial commissioning. • Target, detectors, particle production • Upstream beamline • Downstream beamline: • Step 1 Jan 20 - March , Step 2 April – June. • Summary Kevin Tilley, 16th November. - 75days until commissioning (& 9hours)

  2. Charge. Meaning in commissioning…. Optics goals: Step1 (Jan-March): Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment. Optics goals: Step 2 (April–June): Match beam with diffuser. Find & demonstrate (ε,p) beam cases. Demonstrate purity.

  3. Beamline layout & diagnostic devices

  4. First things first – target, detectors, particle production • Target • Has the target got the required acceleration? • Insert target shallow dip depth, measure reproducibility/flux/loss reproducibility • Insert target into towards 38mm if ISIS beam loss ok, or else acceptable loss. • MICE & Beamline Detectors • Target in, only dipoles on, P(B1=B2)=350MeV/c. Negative polarity (pi-) Calibrate detectors • Particle production • with only dipoles on, P(B1=B2), characterise pion flux versus momentum • relatively simple with MICE PIDs. • ….useful for extrapolating to expected rates.

  5. Step1:- Beamline optics commissioning Optics goals: Step1 (Jan-March): Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment.

  6. Step1:- Upstream beamline optics • Upstream goal:- • Maximum pion flux at detector D1, on axis & aligned pion beam. (=max muon flux, on axis & aligned muon beam. Slightly open question = to confirm this equivalence?) Minimum pion spot size to aid collimation.

  7. Step1:- Upstream beamline optics • Basic optics checks … … (1/2) • Set P(B1=B2) = design setting 444.7MeV/c. • Check basic optics of Q1-Q3. (compare to model) • Individual quads fields scanned:- - measure beamsize changes at U1,D1 - fit to Q1 effective length? - measure beam centroid changes at U1,D1 - fit to any residual target misalignment • Alternatively fields fixed, Target dip change. • - measure beam centroid changes at U1,D1 - refit to any residual target misalignment • Open question:- can beamsize changes & centre changes be seen U1/D1 (strong vert focussing B1, distance to D1)

  8. Step1:- Upstream beamline optics • Basic optics checks………. (2/2) • Set Q1,Q2,Q3, Decay solenoid design optic. • Set P(B1=B2) • Check basic optics of Decay Solenoid:- • Ramp field (beam phase advance), measure beamsize at D1

  9. Step1:- Upstream beamline optics Goal:- Maximum pion flux at detector D1, on axis & aligned pion beam. Minimum pion spot size to aid collimation. • Optimise:- • Set all fields to design settings. P(B2=B1) • Optimisation methods:- 1. Scale (Q1,Q2,Q3) as a single unit, & decay solenoid as a single unit. example:-scaling Q1-Q3 single unit:- 2. Decouple & optimise eg Q1. Optimise 3 parameters:-((Q1,(Q2,Q3),Decay solenoid) 3. Further free up parameters & optimise.

  10. Step1:- Downstream beamline optics • Downstream Goal:- • (Goal of Step1) Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment. • Suggest aim at just one case initially ~(6pi,200MeV/c) Open question: is setting up the downstream beamline with pions of benefit to us? Advantages, but in extreme: are optics for pions suitable for muons? (simulation question) Default is currently to setup beamline with muons until understood.

  11. Step 1:- Downstream beamline optics • Basic optics checks:- (1/1) • B2 scan – backward/forward muon momentum edges. • Basic quadrupole optics – quads in triplets • Open question: has TOF0, TOF1 or Tracker sufficient resolution – with sensible rates? • Use beam monitor as a fallback if not. • Beam misalignment check, by scanning quads fields (near reasonable focus)

  12. Step 1:- Downstream beamline optics Goal: Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment • Measurements:- • Set downstream beamline to have design optics. • Confirm beamsizes at MICE approximately correct. • Measure misalignment at Tracker • Measure transmission efficiency D1- Tracker. • Measure natural emittance of beamline : • (for feeding back to calculate required alpha/beta). • Use 3 tracker planes & TOF assuming muons form 97%, to make offline momentum cuts. • Recalculate desired beamsizes/waists. • Attempt to obtain desired beamsizes/waist… (PTO)

  13. Step1:- Downstream beamline optics Goal: Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment • Optimise :- (Attempting to obtain desired beamsizes/waist) • Optimisation techniques for optimising beamsize/waist in Tracker:- • (some are open questions to answer efficacy) • By hand single lens scaling of (Q456) / (Q789), then decouple in stages. • TRANSPORT envelope fitting: measure beam at Tracker, use known Q789 settings,TOF0 beamsize -> determine input beam at TOF0 -> solve for Q789 for 3-rqd parameters at MICE. • Construct empirical response matrix (in quantites to be determined) and solve for Q4-Q6. • Optimiser .

  14. Step2 – Downstream optics Optics goals: Step 2 (April–June): Match beam with diffuser. Find & demonstrate (ε,p) beam cases. Demonstrate purity. • Similar optimisation techniques to previous slide. .

  15. Summary Goal: Verify can achieve approximately right beamsizes & waists at MICE. Ensure reasonable transmission & flux. Measure alignment • Goals for Step 1 commissioning: proposed • Do upstream optics separately. Sub-goal proposed. • Basic optics • Optimisation • Do downstream separately. Sub-goal proposed. • Basic optics • Optimisation • Goals for Step 2: proposed Goal:- Match beam with diffuser. Find & demonstrate (ε,p) beam cases. Demonstrate purity. • Optimisation of downstream section uses similar techniques to Step1.

More Related