An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alaska Department of Transportation & Public Facilities Akutan Airport Design/Build 2012

  2. Akutan, Alaska

  3. Akutan, Alaska

  4. Trident Seafoods

  5. Grumman Goose

  6. Mountainous Terrain

  7. Mountainous Terrain

  8. Mountainous Terrain

  9. Mountainous Terrain

  10. Selected Alternative

  11. Airport Overview

  12. Marine Link

  13. Akutan Airport Project Budget • Airport $51,441,000 • Access Road $632,000 • Snow Remove Equip $1,748,000 • Sand Building $1,002,000 • Akun Hovercraft Land $2,132,000 • Akutan Amphid. Ramp $330,000 • Akutan Hovercraft Pad $2,374,000 • Akutan Hovercraft Shelter $3,866,000 • Hovercraft $11,000,000 • SRE $814,000 • Total $75,362,000

  14. Co-Sponsorship Agreement The City of Akutan Aleutians East Borough Akutan, Cold Bay, False Pass, King Cove, Nelson Lagoon, Sand Point

  15. Project Funding

  16. Environmental Challenges

  17. Environmental Challenges

  18. Logistics

  19. Weather

  20. Weather

  21. Weather

  22. Weather

  23. Alternative Contract Delivery • Design-Build Contract • Expedited Project Delivery • Potential Innovations • Potential For a More Efficiently Constructable Design

  24. Contract Structure • Design Build Contract • Constructor • Designer • Independent Quality Firm • Design Quality Acceptance • Construction Quality Acceptance • Design Build Support Contract • Design Quality Assurance • Construction Quality Assurance

  25. Alternative Contract Delivery • Cost certainty • 1.2% ($700k) over original contract • $400k adding AWOS • 4.7% GBI ($1.4M) • $1.1M Contaminated Soil • Department Resource Demand • Demand on Department Employees is a fraction of a typical project.