220 likes | 459 Views
Introduction to Materials Management. Chapter 5 – Capacity Management. Basic Capacity Definitions. Capacity Required – capacity needed to produce a desired output in a given time period Capacity Planning – determining the resources and methods needed to meet the priority plan
E N D
Introduction to Materials Management Chapter 5 – Capacity Management
Basic Capacity Definitions • Capacity Required – capacity needed to produce a desired output in a given time period • Capacity Planning – determining the resources and methods needed to meet the priority plan • Capacity Control – monitoring production, comparing with the capacity plan, and taking appropriate corrective actions • Capacity Management – determining capacity needed as well as providing, monitoring, and controlling the capacity
Capacity Planning Levels • Resource Planning – Long range resource requirements linked to the production plan • Rough-cut Capacity Planning – Used to check feasibility of MPS • Capacity Requirements Planning – Detailed work center capacity plans linked to MRP
Capacity Requirements PlanningInputs • Open Order File – found as scheduled receipts on MRP • Planned order releases from MRP – Potential future orders • Work Center file • Information on capacity in the work center • Move, wait, and queue time information
Capacity Requirements PlanningInputs - Continued • Routing file – the path that the work will follow • Operations to be performed • Operation sequence • Work centers used • Potential alternative work centers • Tooling needed • Standard setup times and run times
Sample Routing File Figure 5.3 Routing file
Capacity Available • Impacted by: • Product specification • Product mix • Methods used to make product • Pace of work
Finding Capacity Available • Rated Capacity = (available time) x (utilization) x (efficiency) • Available time : number of hours a work center can be used • Utilization = [(hours actually worked) / (available hours)] x 100% • Efficiency = [(actual production rate) / (hours actually worked)] x 100%
Capacity Load – Sum of all time required for orders on a work center - Example
Scheduling Orders • Back scheduling (the typical approach) – Start with the due date, use lead time to find the proper start date for each operation • Forward scheduling – Launch the order into the first (gateway) work center, then use the lead times to find when the order will be completed at each work center
Back Scheduling Example • An order for 150 of a component is due on day 135 • An order starts at the beginning of a day and finished at the end of a day • Operation times for the 150 ordered: • Operation 10 – 4 days in work center 12 • Operation 20 – 5 days in work center 14 • Operation 30 – 1 day in work center 17 • Operation 40 – 2 days in work center 03
Manufacturing Lead Time • Queue - time spent waiting before operation • Setup - time to prepare the work center • Run - time to make the product • Wait - time spent after the operation • Move - transit time between work centers
Manufacturing Lead Time Queue Setup Run Wait Need a lift truck here Move Move Queue Setup Run Wait
Managing the Plan – Adjusting Capacity • Use Overtime or Undertime • Adjust the number of workers • Shift workers from other work centers • Use alternative work centers to shift load • Subcontract work