An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Brief presentation to begin shortly

  2. Intersection Improvements At US Hwy 431 & Dug Hill Rd City of Huntsville Project No. 65-06-RD12 ALDOT Project No. STPAAF- 0001(531) Public Involvement Meeting September 11, 2007

  3. Vicinity Map

  4. Purpose and Need The purpose of this project is to improve and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431

  5. Poor Intersection Sight Distance from Dug Hill Road to US 431

  6. Improved Intersection Sight Distance from Dug Hill Road to US 431

  7. Purpose and Need The purpose of this project is to improve and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431 • Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road

  8. Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road

  9. Increased Southbound US 431 Deceleration Lane for Dug Hill Road

  10. Purpose and Need The purpose of this project is to improve and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431 • Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road • No Acceleration Lane for Dug Hill Road to US 431 Northbound

  11. No Acceleration Lane for Dug Hill Road to US 431 Northbound

  12. Added Acceleration Lane for Dug Hill Road to US 431 Northbound

  13. Purpose and Need The purpose of this project is to provide improvements and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431 • Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road • No Acceleration Lane for Dug Hill Road to US 431 Northbound • Sub-Standard Acceleration Lane-from Dug Hill Road to US 431 Southbound

  14. Sub-Standard Acceleration Lane from Dug Hill Road to US 431 Southbound

  15. Increased Acceleration Lane from Dug Hill Road to US 431 Southbound

  16. Purpose and Need The purpose of this project is to provide improvements and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431 • Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road • No Acceleration Lane for Dug Hill Road to US 431 Northbound • Sub-Standard Acceleration Lane-from Dug Hill Road to US 431 Southbound • Conflicting Turning Movements Between Dug Hill Road and US 431

  17. Conflicting Turning Movements Between Dug Hill Road and US 431

  18. Separated Turning Movements Between Dug Hill Road and US 431

  19. Purpose and Need The purpose of this project is to provide improvements and increase capacity at the intersection of Dug Hill Road and US Highway 431 in Huntsville, AL. This project is needed due to : • Poor Intersection Sight Distance from Dug Hill Road to US 431 • Sub-Standard Southbound US 431 Deceleration Lane for Dug Hill Road • No Acceleration Lane for Dug Hill Road to US 431 Northbound • Sub-Standard Acceleration Lane-from Dug Hill Road to US 431 Southbound • Conflicting Turning Movements Between Dug Hill Road and US 431 • Excessive Delays for motorists traveling Dug Hill Road on to US 431

  20. Excessive Delays for motorists traveling Dug Hill Road on to US 431

  21. Excessive Delays for motorists traveling Dug Hill Road on to US 431

  22. Decreased Delay for motorists traveling Dug Hill Road on to US 431

  23. Proposed Improvements The proposed Dug Hill Road/ US 431 Improvements project will include: • Increased deceleration lane for Southbound US 431 to Dug Hill Road. • Free Flow Movement from Dug Hill Road to Northbound US 431 with Acceleration Lane. • Offset Left Turn Movements from Southbound US 431 to Dug Hill Road and Dug Hill Road to Southbound US 431 • Increased Dug Hill Road to Southbound US 431 Acceleration Lane • Increased Sight Distance at US 431 & Dug Hill Road Intersection • Intersection Lighting and Additional Warning Devices

  24. Proposed Design

  25. Active Model of Improvements

  26. Project Accomplishments to Date • November 21, ‘06 – Contract between City of Huntsville and J&A executed • February ’07 – Obtained Design Criteria Approval from ALDOT • March ’07 – Began Environmental/Corridor Studies • April ’07 – Submitted Cultural Resources Survey (Environmental) • May 11, ’07 – Submitted 30% Complete plans for ALDOT and COH review • June 26, ’07 – Held 30% Review with ALDOT & COH • July ’07 – Began Geotechnical Investigations & Materials Report • June to August ’07 – Studied Alternatives for Legacy Preserve Entrance • September 11, ’07 – Holding Public Involvement Meeting

  27. Goal Dates for Remaining Project Tasks • * September 28, ’07 – Submit for Plan-In-Hand (70% Complete) Review • * October 19, ’07 – Submit Environmental Document (Categorical Exclusion) for ALDOT and FHWA Review and Approval with a request for exemption from a Public Hearing • * October 31, ’07 – Submit Geotechnical & Materials Report for review & approval • Late November, ’07 – Environmental Document Approved; signatures obtained • December ’07 – Right-of-Way can be Authorized for Acquisition • Late December, ’07 – P.S. & E. (90% Complete) plans submitted for ALDOT & COH Review • Late Spring ’08 – Plans Complete; Ready to advertise for Construction • Summer ’08 – Right-of-Way acquired; Rights of Entry Executed • Late Summer/Early Fall ’08 – Construction Begins * = Goals that can be accomplished Independent of FHWA & ALDOT review

  28. Questions and Comments