INSIGHTS FROM THE AUCKLAND MOTORWAY ALLIANCE . 12 July 2013 Richard Steel Project Director, Beca Ltd. Procurement Process. Providing for Change. Applicability of delivery assumption . Certainty of variations. Degree of Certainty . Driven By: Technology Standards Regulations
E N D
INSIGHTS FROM THE AUCKLAND MOTORWAY ALLIANCE 12 July 2013 Richard Steel Project Director, Beca Ltd
Providing for Change Applicability of delivery assumption Certainty of variations Degree of Certainty • Driven By: • Technology • Standards • Regulations • Levels of service • Asset changes • Driven By: • Production rate • Utilisation • Access times • Technology • Methodology 10 yrs
Maintaining Price Tension 30 June 2018 1 Oct 2008 1 July 2015 1 April 2008 1 July 2012
Observations • NZTA appointed Alliance Director has been a positive • Strong tactical asset management and efficiency drivers: • 3 year TOC periods • TOC and KRA/KPI and LoS resets • Challenges and Opportunities • Valuing initiatives with long term benefits (beyond TOC period) • Diminishing opportunity for efficiency gains • Maintaining a virtual business rather than developing a bureaucracy