970 likes | 1.2k Views
Flight Readiness Review (FRR). Charger Rocket Works University of Alabama in Huntsville NASA Student Launch 2013-14. Kenneth LeBlanc (Project Lead) Brian Roy (Safety Officer) Chris Spalding (Design Lead) Chad O’Brien (Analysis Lead) Wesley Cobb (Payload Lead).
E N D
Flight ReadinessReview (FRR) Charger Rocket Works University of Alabama in Huntsville NASA Student Launch 2013-14 Kenneth LeBlanc (Project Lead) Brian Roy (Safety Officer) Chris Spalding (Design Lead) Chad O’Brien (Analysis Lead) Wesley Cobb (Payload Lead)
Prometheus Flight Overview Payloads Here
Technology Readiness Level http://web.archive.org/web/20051206035043/http://as.nasa.gov/aboutus/trl-introduction.html
Outreach • Adaptable for different ages and lengths • Supporting activity • Water Rockets • Completed • Science Olympiad • Challenger Elementary • Discovery Middle • Horizon Elementary • Numbers • Education Direct: 466 • Outreach Direct and Indirect: 723
Design Team Members:
5 1 2 3 4 Hardware Changes: Printed Nylon Transition coupler to accommodate nose cone mold error Flat bulk head and additional coupler joint Flat bulk head ABS plastic Brackets secured with Chicago screws • Design Details: • 34lbs • 40Gs acceleration • Geometric similarity to NASA Nanolaunch prototype • Nanolaunch team requested maximum use of SLS printed aluminum
Thrust Ring • Machined 5086 Aluminum • Will be Analyzed with FEA
Fin Assemblies Currently have sets of fin brackets in abs plastic and fiber reinforced nylon. • ABS has been proof loaded to 75 lbs • 3D printed Laser sintered nylon brackets have been ordered • Bolted to body • Binding post fin attachment
Body Tube • Three body tube pieces joined with nylon printed couplers • Carbon composite • FEA, destructive testing and hand calculations done to assess strength • Large margin of safety and low weight
Payload Shaft • 7075-T6 Aluminum threaded shaft 3/8-16 • Preloaded in tension • FEA and hand calculations show significantly over strength requirements
Payload Shaft Load Paths • Carries thrust loads into payloads and recovery forces into lower rocket, as well as providing assembly method for payloads, body tubes and recovery harness • Red Arrow indicates motor loads from thrust ring through body tube • Green arrow indicates motor loads passed through payloads • Blue arrow indicates recovery forces passed through payload shaft • Orange arrow indicates motor case retention force
Coupler Rings • Sintered nylon (potentional to be reinforced with aluminum or carbon fiber) • Aft coupler retained by payload shaft preload. Also, one side will be epoxied to the body tube. • Fore coupler retained by nose cone shaft and shear pins
Nose Cone Assembly • All components retained by shaft similar to payload shaft • Carbon fiber nose cone shroud and bulkhead • Bulkhead is secured with tension from the nose cone payload shaft (seen on next slide) • Contains pitot pressure and accelerometer/ gyro data package
Nose Cone Assembly • Coupler is designed for slip fit and secured with shear pins. Secured with tension in the payload rod. • The new design allotted more space for the recovery system
Pitot Probe • Allows measurement of static pressure along with supersonic AND subsonic total pressure • Unique and original design which could only be made with 3D printing techniques • Helps fulfill our Nanolaunch request to explore selective laser sintering in original ways. Old Design
Pitot Probe Manufactured out of glass reinforced nylon. • Secured with threaded insert epoxied into center (blue part) • Connection ports are now open to attachment by epoxying tube directly • The change allowed for simplified 3D printing New Design
Analysis Team Members:
Prometheus Simulation • RockSim Software Package • Motors • Primary: CTI4770 – 98mm • Secondary: AeroTech K1499 – 75mm • Estimated Dry Mass at 27 lbs • Launch Conditions for Salt Lake City • ASL – 4210 feet • Temperature – 72 ˚F
Final Motor Selection - CTI M4770-P • ISP – 208.3s • Loaded Weight: 14.4lb • Propellant Weight: 7.3 lb • Max Thrust: 1362 lbf
Prometheus’ Static Margin • Launch Static Margin – 1.7 • Burnout Margin – 4.5 CG at 85.8” CP at 93.6”
Prometheus Simulation • Max Altitude – 15,700 feet • Max Velocity – 1600 feet per second • Max Acceleration – 40 Gs
Prometheus’ Static Margin • Pre-Launch Static Margin: 1.7 • Burnout Static Margin: 4.5
MonteCarloAnalysis Altitude: Mach: Accleration:
Drift Analysis • 500 Cases for each cross wind. • High probability of landing within the 5000 foot requirement
Variation in Flight Time • Time variance directlyaffects the radial landingdistance. • Dependent on high speedcoefficient of drag for drogue
Plan B Motor: Aerotech K1499 • Altitude – 2100 feet • Velocity – Mach 0.25 • Acceleration – 16 G’s
The Equations for Fin velocity • t = thickness of fin • AR = aspect ratio • l = taper ratio • G = shear modulus. • C = root chord • P = air pressure • a = speed of sound
The Equations for Fin Velocity • S - Wing Area • b - Semi-span • Cr - root chord • Ct - tip chord • T - Temperature of air • Area = 0.5(Ct + Cr)b • AR = b2/S • l = Ct/Cr
Prometheus Fin Given:
Assumptions • Shear Modulus: 5E5 psi • Isotropic Layup • Applied Max Velocity of 2000 ft/s • Solved for Material Thickness
Conclusion • At exactly t = 0.17 inches, max V = 2071 ft/s • Designed Max V = 2000 ft/s • Projected Max V = 1600 ft/s • The safety range is accounted for with current design and material of Prometheus
Buckling Analysis • Used Euler’s Buckling Equations
Recovery System • Single Separation Point • Main Parachute • Hemispherical • 12 ft • Cd 1.3 ( flight test) • Nylon • Drogue Parachute • Conic • 2.5 ft • Cd 1.6 (flight test) • Nylon
Deployment Bag • NomexFabric • Kevlar Thread • Fiberglass Rod Inserts for Rigidity • Shroud line “daisy chained” and coiled in bag section. Bag Section Fiberglass Rod inserts
Main Parachute • 12 Feet Semi-Hemispherical • Ripstop Nylon • Custom Seam • 14 Gores • Shroud Lines: 0.125in x 550lb Paracord
Sewing Technique • Multi Method Gore Stitch • Straight stitch • Zigzag stitch • Biased Tape Reinforced Joints • Edges hemmed using serge roll. • Joints Reinforced with Nylon Straps. Seam Cross Section
Recovery System Deployment Process • Stage 1 • 2 seconds after apogee • nose cone separates • release the drogue • Stage 2 • The Tender Desenders release • Stage 3 • Main parachute falls out deployment bag/burrito Eye bolt Drogue L.H.D.S Main Parachute InDeployment bag/Burrito Tethers Black Powder Charge
Deployment Process Stage 1: Drogue Deployment Stage 2: Tether Separation Stage 3: Final Decent
GPS Tracking • GPS Module: Antenova M10382-Al • GPS lock from satellites • Transmits data through XBee RF module • 8 ft accuracy with 50% CEP (Circular Error Probable) • 3.3 VDC supply voltage • 22 to 52 mA current draw • Since CDR, redundant GPS Unit: “Tagg Pet Tracker” no longer included
Radio Transmission • RF Module: XBee-PRO XSC S3B • 900 MHz transmit frequency • 20 Kbps data rate • 9 mile LoS range • 250 mW transmit power • 3.3 VDC supply voltage • 215 mA current draw • 1.5+ hr battery life at max sensor sample rate • Laptop ground station