430 likes | 914 Views
LIGHTWEIGHT CONCRETE BENEFITS FOR PBES DEPLOYMENT Reid W. Castrodale, PhD, PE Director of Engineering Carolina Stalite Company, Salisbury, NC. Learning Outcomes. After completing this Module, you will be able to: describe how lightweight aggregate is manufactured
E N D
LIGHTWEIGHT CONCRETE BENEFITS FOR PBES DEPLOYMENTReid W. Castrodale, PhD, PEDirector of EngineeringCarolina Stalite Company, Salisbury, NC
Learning Outcomes After completing this Module, you will be able to: describe how lightweight aggregate is manufactured identify the classifications of lightweight concrete identify several advantages of using lightweight concrete for PBES bridges recall several PBES projects where lightweight concrete was or could have been used
Development of LWC • In early 1900s, Stephen Hayde discovered method to manufacture lightweight aggregates (LWA) from shale, clay and slate • Some bricks bloated during burning • Development of rotary kiln process began in 1908 • Patent for expanding LWA using a rotary kiln process was granted in 1918 • The first use of lightweight concrete (LWC) was for ships in World War I
Development of LWC • Early use of LWC in a bridge project • San Francisco-Oakland Bay Bridge • Upper deck of suspension spans was constructed using LWC in 1936 • Lower deck was rebuilt with LWC for highway traffic in 1958 • Both decks are still in service
Structural LWA • LWA is manufactured • Raw material is shale, clay or slate • Expands in kiln at 1900 – 2200 deg. F • Gas bubbles formed in softened material are trapped when cooled
Relative Density • Rotary kiln expanded LWA • Range from 1.3 to 1.6 • Normal weight aggregate • Range from 2.6 to 3.0 • Twice the volume for same mass • Half the mass for the same volume Soil Sand Gravel ESCS Agg. Limestone 1 lb. of each aggregate
LWA is lighter than NWA But LWA still satisfies typical specifications required of NWA for use in most construction applications Different gradations – AASHTO M 195 A non-concrete application for LWA Geotechnical fill Can be used on ABC projects 7 LWA is just a lighter rock!
Geotechnical Use of LWA LWA can be used as structural fill LWA is free draining 8
Pentagon Secured Entrance LWA fill was used between MSE walls • Reduced anticipated settlement from 15” to 6” • Reduced settlement time from 180 days to 60 days • Enabled contractor to meet tight project schedule
When LWA is used to make LWC Same batch plants and mixing procedures Same admixtures Can use same mix design procedures “Roll-o-meter” for measuring air content LWA has higher absorption than NWA Needs to be prewetted, especially for pumping Visit ESCSI website or contact LWA supplier for more info on properties of LWA and LWC 10 LWA is just a lighter rock!
Most common Lightweight Concrete • LWA is used to reduce density of concrete • “All lightweight” – all aggregates, both fine and coarse, are lightweight • “Sand lightweight” – lightweight coarse aggregate and normal weight sand • “Specified density” – blend of NW and LW aggregate to achieve target density (SDC) • Density of LWC is checked during placement for QC
Definitions • AASHTO LRFD Specs (Section 5.2) • Lightweight concrete: "Concrete containing lightweight aggregate and having an air-dry unit weight not exceeding 0.120 kcf …" • Normal weight concrete: “Concrete having a weight between 0.135 and 0.155 kcf” • Concrete that falls between these definitions is often called specified density concrete (SDC)
Spectrum of Concrete Density Specified Density Concrete (SDC) Density ranges shown are approximate Must add allowance for reinforcement (typ. 5 pcf)
Specifying Density of LWC • “Equilibrium density” is defined in ASTM C 567 • Density after moisture loss has occurred over time • Often used for dead load calculations • “Fresh density” used for QC tests during casting • Designer or supplier must specify • Must use for precast member weight at early age • May use for final design loads for large elements • Add reinforcement allowance to concrete density when computing dead loads (typ. 5 pcf)
Sand LWC for Bridge Decks TennDOT includes in Standard Specifications NCDOT, UDOT, etc. have std special provisions Other states have project special provisions All LWC Has not been used in recent years Special provisions have been developed for NCDOT DOT Specifications for LWC
Semi-LWC for Girders INDOT allows in design manual (120-130 pcf) Recurring special provisions being developed Sand LWC for Girders GDOT has special provisions (10 ksi at 120 pcf) VDOT has special provisions (8 ksi at 125 pcf) Approved aggregate lists A number of states have approved LWA sources DOT Specifications for LWC
GDOT Special Provisions Special provisions for 10 ksi sand LW HPC girders Maximum air-dry density is 120 pcf Size of LW coarse aggregate = ½ in. Minimum cement factor = 650 lbs/cy Maximum water-cement ratio = 0.330 Slump acceptance limits = 4½ ± 2½ in. Entrained air acceptance limit = 5 ± 1½ % Max. chloride permeability = 3,000 coulombs Same as for NW HPC, except density & aggr. size
Reduced weight of precast elements Improves handling, shipping and erection Can also improve structural efficiency Enhanced durability Reduced cracking tendency Reduced permeability Tighter quality control with a specified density LWC can be used to achieve both accelerated constructionandlonger-life structures 18 Benefits of Using LWC Focus of webinar Opposite of what many expect!
Enhanced Durability Improved bond between aggregate & paste Elastic compatibility Internal curing Reduced cracking tendency Improved resistance to chloride intrusion Increased fire resistance Enhanced resistance to freezing & thawing Good wear and skid resistance Alkali-silica reactivity (ASR) resistance 19
Cost of LWC • Increased cost of LWA • Additional processing • Shipping from the manufacturing plant
Cost Premium for LWC • Effect of sand LWC deck on cost of bridge • Cost / SF assumes 9 in. thick deck (average) • Premium depends on cost of LWA, cost of NWA being replaced, and shipping cost
Effect of sand LWC girders on cost of bridge Assume $30 / CY cost premium for sand LWC Girder spacing assumed to be 10 ft Cost Premium for LWC
Sample Girder Cost Analysis • Cost premium for sand LWC in Mod BT-74 girder • Assume $30 / CY = $6.83 / LF • Cost premium for LWC for 150 ft girder =$1,024 • Cost reduction by using sand LWC girder • Shipping from plant to site = $811 • NWC girder = 69 t; LWC girder = 58 t, or 11 t less • Drop 4 strands / girder @ $0.65 / LF ea. = $390 • Total cost reduction =$1,201 • Net savings by using sand LWC girder $177
PBES Applications for LWC • Sand LWC & Specified Density Concrete • Use for any precast or prestressed conc. elements • All LWC • Can be used for any precast concrete element • Data not yet available for prestressed elements These are fresh densities for concrete up to about 6 ksi Add 5 pcf allowance for reinforcement
Consider sample projects Precast foundation elements Precast pile & pier caps Precast columns Precast full-depth deck slabs Cored slabs & Box beams NEXT beams & Deck girders Full-span bridge replacement units with precast deck Bridges installed with SPMTs Impact of LWC on PBES
Mill Street Bridge, NH • Precast foundation elements • Project did not use LWC • Comparison for abutment footings • Abutment walls have similar weights
Okracoke Island, NC • Precast pile caps • Project did not use LWC • End bent pile cap – 2 pieces • Size: 21 ft long x 3.67 ft x 3 ft • 3 pile pockets per piece
Lake Ray Hubbard, TX • Precast pier caps • Project did not use LWC • Typical pier cap on 3 columns • Size: 37.5 ft long x 3.25 ft x 3.25 ft
Edison Bridges, FL • Project did not use LWC • Precast columns • Max wt = 45 tons @ 150 pcf • Max wt = 37 tons @ 125 pcf • Using 128 pcf SDC could have eliminated pedestal for tall columns • Precast caps • Max wt = 78 tons @ 150 pcf • Max wt = 65 tons @ 125 pcf
Woodrow Wilson Br, VA/DC/MD • Deck replacement with full-depth precast deck panels in 1983 • Sand LWC was used for panels • Allowed thicker deck • Allowed widened roadway with no super- or substructure strengthening • Reduced shipping costs and erection loads • Sand LWC deck performed well until bridge was recently replaced to improve traffic capacity
Okracoke Island, NC • Precast cored slabs • Project did not use LWC • 21” deep by 3 ft wide • 30 and 50 ft spans
Okracoke Island, NC • Precast barriers • Project was not designed with LWC • Contractor proposed casting barriers on cored slabs in precast plant • Sand LWC was used for the barrier
Mill Street Bridge, NH • Precast box beams • Project did not use LWC • NWC box beam weight governed crane size with 2 crane pick • Using sand LWC for box beam would make beam pick nearly equal to NWC substructure elements
NEXT F Beams 16% 8 ft 10 ft 12 ft 8 ft 10 ft 12 ft • Compare section weights for NEXT 36 F • NWC @ 155 pcf; Sand LWC @ 130 pcf • No max. span charts for sand LWC • 16% reduction in weight for same width sections • 12 ft wide LWC is lighter than 8 ft wide NWC
NEXT D Beams 16% 8 ft 10 ft 12 ft 8 ft 10 ft 12 ft • Compare section weights for NEXT 36 D • 12 ft width not used to limit weight of NWC section • Max. span charts are provided for sandLWC • 16% reduction in weight for same width sections • 12 ft LWC is lighter than 10 ft NWC
Deck Girders, NY • Precast deck girder • Project did not use LWC • 41” deep deck girders with 5 ft top flange • 87.4 ft long girders NWC density was obtained from girder fabricator Specified concrete compressive strength = 10,000 psi
I-95 in Richmond, VA • Prefabricated full-span units • Steel girders and sand LWC deck • Maximum precast unit weight for current project Deck densities do not include reinforcement allowance
Lewis & Clark Bridge, OR/WA • Deck replacement on existing truss • Sand LWC precast deck units with steel floor beams • Sand LWC density = 119 pcf • Max. deck unit weight = 92 t • Sand LWC saved about 14 t • Existing deck was LWC • Was in service 73 years
Bridges set with SPMTs, UT • 3300 South over I-215 – Built in 2008 • Sand LWC used for deck • Less deck cracking than bridges with NWC decks • 3 bridges to be moved in 2011 • Steel girder bridges with sand LWC decks • 200 South over I-15 – 2 spans @ 3.1 million lbs • Sam White Lane over I-15 – 2 spans @ 3.8 million lbs • I-15 Southbound over Provo Center Street • 2 moves of 1.5 and 1.4 million lbs
Graves Ave. over I-4, FL • Complete span replaced using SPMTs • Project did not use LWC • Comparison of weight for NWC and sand LWC • Appendix C in FHWA “Manual on Use of SPMTs …” Comparison with all LWC deck is not in Manual
Conclusions You should now be able to: • describe how lightweight aggregate is manufactured • identify the classifications of lightweight concrete • identify several advantages of using lightweight concrete for PBES bridges • recall several PBES projects where lightweight concrete was or could have been used
Questions? For more information on LWA and LWC • Contact Reid Castrodale: rcastrodale@stalite.com • Visit the Expanded Shale, Clay and Slate Institute website: www.escsi.org • Contact local LWA suppliers: listed on ESCSI website