An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Test Prep 1 Selected Questions

  2. 5. An egoless approach structure team has 15 members. What is the number of lines of communication for this team? • a. 105 • b. 15 • c. 225 • d. 150

  3. 9. Which of the following is not a part of the project plan? • a. Test plan • b. Configuration management plan • c. Requirements definition document • d. Project team organization

  4. 7. In a project being developed by AB Corp., an activity requires 15 days to complete. However, 17days have been allotted for its completion. What is the slack time and if today is September 1, 2004,when can this activity begin at the latest? • a. 17, September 1, 2004 • b. 15, September 2, 2004 • c. 32, September 15, 2004 • d. 2, September 3, 2004

  5. 1. ABC Corp. developed a system and delivered it to the customer last summer. The customer has requested a change in the system. Brett Lewis, the designer, is analyzing where the changed requirement should be placed. To which team does Brett belong? • a. Test team • b. Development team • c. Configuration management • d. Maintenance team

  6. 11. ABC Corp. is analyzing requirements for their project. The analysts want to analyze the entities in the system and the hierarchical relationship between the entities. Which analysis model will theanalysts have to create for this? • a. Data flow diagrams • b. Event tables • c. Transition diagrams • d. Object-oriented specification diagrams

  7. 8. AB Corp. is developing a project which has a risk probability of 0.4. AB Corp. has estimated that in case the eventuality occurs, the company will need to invest an extra $20,000 in the project. Identify the risk exposure: • a. 20,000 • b. 0.4 • c. 50000 • d. 8000

  8. 2. Which process model is most suitable for a project that has a large number of risks? • a. Waterfall • b. Spiral • c. Prototyping • d. Incremental

  9. 3. PQR Corp. has recently been assigned a prestigious project by the government. The project is an AI-based innovative system for managing security at various government buildings. Although advertised as a revolutionary security system, government officials handling the project have listed a vague set of requirements. In addition, the officials want to witness a quick demonstration of the system within two to three months because they will finalize the exact requirements of the system after the demonstration. Which model would be best suited for the project? • a. Spiral • b. Waterfall • c. Incremental • d. Prototyping

  10. 16. Which of the following is the worst form of cohesion? • a. Communicational • b. Logical • c. Sequential • d. Coincidental

  11. 6. Alex is a member of a software development team. Alex makes all decisions logically after gathering complete information. However, Alex usually judges peers by how busy they are and mostly asks them queries related to the project. He does not prefer taking initiative and telling them about new findings or information related to the project. Alex is very dedicated about work and strives for accuracy. Which working style would you classify Alex into? • a. Intuitive Introvert • b. Intuitive Extrovert • c. Rational Introvert • d. Rational Extrovert

  12. 15. A good design has which of the following characteristics? • a. High coupling, low cohesion • b. Low coupling, high cohesion • c. High coupling, high cohesion • d. Low coupling, low cohesion

  13. 4. Which phase follows the system testing phase in the waterfall model? • a. Coding • b. Unit testing • c. Acceptance testing • d. Integration testing

  14. 10. ABC Corp. has hired you as a technical consultant for a project that has been planned and finalized with the customer. In addition, ABC Corp. has held requirements elicitation sessions with thecustomer to finalize the requirements. As a technical consultant you are responsible for all documentations related to the project. Which documentation is scheduled for this project now? • a. Project plan • b. Configuration management plan • c. Requirements definition document • d. SRS

  15. 14. PQR Corp. is developing an employee record management system. It will deal with two types of employees – those who earn salaries and those who get wages. The system being developed for allemployees must store some data in common such as their names, addresses, etc. However, some details such as remuneration and calculation formulae are different for the two categories. The analyst is depicting these requirements in an object-oriented specification diagram with employees, salaried employees and employees earning wages, as separate entities. Which object-oriented concept could the analyst be using for the above scenario? • a. Encapsulation • b. Abstraction • c. Inheritance • d. None, except for simple objects, methods, and properties